PD-PASA run Wed 25 Nov 01:00 (to Thu 26 Nov 04:00) · ST-PASA run Wed 25 Nov 00:00 · MT-PASA published Tue 24 Nov 18:00 · times AEST · units out = ≥50 MW below capacity

Supply impact · NEM

Coal out
6,135 MW of 21,255 MW (29%)
All scheduled plant out
9,635 MW
Coal 6,135 · Gas 2,503 · Hydro 997
Operational demand now
20,324 MW
30-min interval · 01:00
Out as % of demand
47.4%
Spot price now (demand-weighted)
87 $/MWh
5-min interval · 01:15
RegionCoal capacity MWCoal out MWCoal % outScheduled out MWDemand MWPrice $/MWh
NSW8,3052,98036%3,4936,83089
QLD8,1301,89523%3,0076,23790
VIC4,8201,26026%2,1524,88982
SA–––3631,40984
TAS–––62095988
NEM21,2556,13529%9,63520,32487

Generator outages · 9,635 MW total

NSW QLD SA TAS VIC

MW out, now to 7 days · NEM

Units out now · 40 units

UnitStationRegionFuelCapacity MWAvailable MWMW outTypeBack within weekMT-PASA returnRecall (h)
ER04EraringNSWCoal7200720UnplannedThu 26 Nov 11:30Thu 26 Nov 20260.0
BW04BayswaterNSWCoal6850685Not in MT-PASAMon 30 Nov 04:30—Long-term
BW03BayswaterNSWCoal6850685Plannedbeyond 7 daysMon 21 Dec 2026Long-term
MP2Mt PiperNSWCoal6600660Not in MT-PASATue 01 Dec 04:30—Long-term
LYA1Loy Yang A Power StationVICCoal5600560Plannedbeyond 7 daysWed 02 Dec 2026Long-term
NPSNewportVICGas5000500PlannedMon 30 Nov 04:30Mon 30 Nov 2026Long-term
MPP_1Millmerran Power PlantQLDCoal4260426PlannedSat 28 Nov 08:00Sat 28 Nov 20260.0
KPP_1Kogan CreekQLDCoal744320424UnplannedWed 25 Nov 10:00Fri 04 Dec 2026Long-term
STAN-2StanwellQLDCoal3650365Plannedbeyond 7 daysWed 02 Dec 20260.0
TARONG#3TarongQLDCoal3500350PlannedMon 30 Nov 05:30Sun 29 Nov 20260.0
YWPS1Yallourn WVICCoal3500350Not in MT-PASAWed 25 Nov 13:00—Long-term
YWPS2Yallourn WVICCoal3500350Plannedbeyond 7 daysMon 14 Dec 2026Long-term
GSTONE1GladstoneQLDCoal2800280UnplannedFri 27 Nov 09:30Fri 27 Nov 2026Long-term
TVCC201Tamar Valley Combined CycleTASGas2080208Plannedbeyond 7 daysTue 04 May 20270.0
TORRB2Torrens Island BSAGas2000200Plannedbeyond 7 daysFri 18 Dec 2026Long-term
BRAEMAR2BraemarQLDGas1880188PlannedSun 29 Nov 18:30Mon 30 Nov 2026Long-term
BRAEMAR3BraemarQLDGas1880188PlannedMon 30 Nov 18:30Tue 01 Dec 2026Long-term
YARWUN_1Yarwun 1QLDGas1800180Plannedbeyond 7 daysMon 11 Jan 2027Long-term
URANQ13UranquintyNSWGas1730173UnplannedSat 28 Nov 16:30Sun 29 Nov 20260.0
URANQ14UranquintyNSWGas1730173PlannedSat 28 Nov 16:30Sun 29 Nov 20260.0
SHGENShoalhavenNSWHydro24780167Unplannedbeyond 7 daysSat 17 Jul 20270.0
YABULUTownsville Power Staton - QPMQLDGas1600160Not in MT-PASAbeyond 7 days—Long-term
MCKAY1Bogong / MackayVICHydro300145155Plannedbeyond 7 daysFri 04 Dec 2026Long-term
GORDONGordonTASHydro432288144Plannedbeyond 7 daysbeyond horizon0.0
TUNGATINTungatinahTASHydro1250125Unplannedbeyond 7 daysbeyond horizon0.0
KIDSPHG2Kidston Pumped Hydro (gen 2)QLDHydro1250125Plannedbeyond 7 daysThu 22 Jul 2027Long-term
KIDSPHG1Kidston Pumped Hydro (gen 1)QLDHydro1250125Plannedbeyond 7 daysThu 22 Jul 2027Long-term
ER02EraringNSWCoal720600120Unplannedbeyond 7 daysSun 06 Dec 20260.0
AGLSOMSomertonVICGas1708090Plannedbeyond 7 daysFri 04 Dec 2026Long-term
MINTAROMintaro GTSAGas90090Not in MT-PASAThu 26 Nov 04:30—Long-term
CETHANACethanaTASHydro85085Plannedbeyond 7 daysSat 27 Feb 20270.0
YABULU2Townsville Power Staton - QPMQLDGas84084Plannedbeyond 7 daysbeyond horizonLong-term
JLB01Jeeralang BVICGas76076PlannedThu 26 Nov 07:30Thu 26 Nov 2026Long-term
AGLHALHallett GTSAGas27720473Plannedbeyond 7 daysWed 31 Mar 20270.4
MURRAYMurray 1VICHydro1,5501,47971Plannedbeyond 7 daysbeyond horizon84.0
CPSACondamine AQLDGas1448262Plannedbeyond 7 daysbeyond horizon0.0
ER03EraringNSWCoal72066060Not in MT-PASATue 01 Dec 09:30—0.0
TVPP104Tamar Valley PeakingTASGas58058Plannedbeyond 7 daysSat 05 Dec 20260.0
TNPS1Tarong NorthQLDCoal45040050Plannedbeyond 7 daysThu 01 Apr 20270.0
ER01EraringNSWCoal72067050Not in MT-PASAWed 25 Nov 08:30—0.0
Mothballed or retired, not counted: SNUG1 63 MW, POR01 50 MW
Data: AEMO PD-PASA, ST-PASA, MT-PASA · plot: ITK