AEMO High Impact Outages report of 23 Nov 2026 (weekly) · consecutive outages of one asset within 2 days are merged
In progress · 2
| Region | NSP | Network asset | Start | Finish | Status |
|---|
| NSW | Transgrid | Marulan � Bannaby (35) 330kV Line | 24 Nov 2026 07:00 | 25 Nov 2026 16:00 | Planned - STLTP |
| VIC | AusNet | Koorangie - Wemen 220kV line | 21 Nov 2026 07:40 | 23 Nov 2026 15:00 | In Progress - PTP |
Unplanned
No unplanned outages listed.
Planned, next 30 days · 11
| Region | NSP | Network asset | Start | Finish | Status |
|---|
| VIC | AusNet | Rowville - South Morang 500 kV Line | 26 Nov 2026 05:30 | 26 Nov 2026 16:00 | Planned - MTLTP |
| NSW | Transgrid | Canberra � Capital (6) 330kV Line | 26 Nov 2026 06:00 | 14 Dec 2026 16:00 | Planned - MTLTP |
| QLD | Powerlink | Nebo - Strathmore (822) 275 kV Line | 26 Nov 2026 12:00 | 26 Nov 2026 16:00 | Planned - STLTP |
| VIC | AusNet | Hazelwood - South Morang No.2 500 kV Line (4 periods) | 30 Nov 2026 05:30 | 03 Dec 2026 17:00 | Planned - SUBMIT |
| NSW | Transgrid | Tamworth No.5 330 kV Bus | 09 Dec 2026 04:00 | 09 Dec 2026 12:00 | Planned - RESUBMIT |
| TAS | TasNetworks | George Town - Comalco 5 220kV LINE | 09 Dec 2026 06:00 | 09 Dec 2026 18:00 | Planned - RESUBMIT |
| QLD | Powerlink | Broadsound - Nebo (834) 275 kV Line | 10 Dec 2026 09:00 | 10 Dec 2026 17:00 | Planned - MTLTP |
| QLD | Powerlink | South Pine - Tarong (832) 275 kV line | 14 Dec 2026 08:00 | 14 Dec 2026 16:00 | Planned - SUBMIT |
| NSW | Transgrid | Lower Tumut - Wagga (51) 330 kV Line | 15 Dec 2026 06:00 | 15 Dec 2026 17:00 | Planned - SUBMIT |
| NSW | Transgrid | Rye Park Wind Farm � Gullen Range Wind Farm (3P) 330kV Line | 15 Dec 2026 06:00 | 20 Dec 2026 16:00 | Planned - MTLTP |
| QLD | Powerlink | Nebo - Strathmore (822) 275 kV Line | 16 Dec 2026 12:00 | 16 Dec 2026 16:00 | Planned - RESUBMIT |
Inter-regional, next 12 months · 11
| Region | NSP | Network asset | Start | Finish | Status |
|---|
| NSW | Transgrid | Tamworth No.5 330 kV Bus | 09 Dec 2026 04:00 | 09 Dec 2026 12:00 | Planned - RESUBMIT |
| NSW | Transgrid | Lower Tumut - Wagga (51) 330 kV Line | 15 Dec 2026 06:00 | 15 Dec 2026 17:00 | Planned - SUBMIT |
| NSW | Transgrid | Muswellbrook - Tamworth (88) 330 kV Line | 03 Mar 2027 04:00 | 04 Mar 2027 14:00 | Planned - SUBMIT |
| NSW | Transgrid | Tamworth Liddell PS (84) 330 kV Line | 09 Mar 2027 04:00 | 10 Mar 2027 14:00 | Planned - SUBMIT |
| NSW | Transgrid | Lower Tumut - Wagga (51) 330 kV Line | 15 Mar 2027 04:00 | 19 Mar 2027 17:00 | Planned - RESUBMIT |
| NSW | Transgrid | Wagga - Darlington Point (63) 330 kV Line | 16 Mar 2027 05:00 | 16 Mar 2027 17:00 | Planned - SUBMIT |
| NSW | Transgrid | Lower Tumut - Wagga (51) 330 kV Line | 09 Jun 2027 07:00 | 15 Jun 2027 17:00 | Planned - SUBMIT |
| NSW | Transgrid | Armidale - Tamworth (86) 330 kV Line (2 periods) | 03 Aug 2027 07:00 | 21 Aug 2027 17:00 | Planned - SUBMIT |
| NSW | Transgrid | Tamworth No.3 330 kV Bus | 30 Aug 2027 07:00 | 30 Aug 2027 17:00 | Planned - SUBMIT |
| NSW | Transgrid | Armidale - Tamworth (86) 330 kV Line (2 periods) | 31 Aug 2027 07:00 | 18 Sep 2027 17:00 | Planned - SUBMIT |
| NSW | Transgrid | Armidale - Tamworth (86) 330 kV Line | 28 Sep 2027 07:00 | 09 Oct 2027 16:00 | Planned - SUBMIT |
37 later inter-regional outages (to 2036) not shown
Data: AEMO High Impact Outages · plot: ITK