NEM Dashboard

ITK
Period

Commissioning / hold point constraint for Orana BESS of +415MW - HP4

NSW · Other · C_N_ORABESS1_415_G
Most frequent constraint: Commissioning / hold point constraint for Orana BESS of +415MW - HP4
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
5
% of period
0.2%
Network as built share
0.0%
Equipment outage share
0.0%
Single-plant limit share
100%
Units in constraints
1
MW in constraints
415
Curtailed while constrained
0.0 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
N_ORABESS_L_D82_N1415Limit on a single plantSystem StrengthOrana BESS inverter limit of 82 during daytime and 141 during nighttime. Constraint to violate if Orana as a load inverter availability greater than 82 during daytime or 141 during nighttime. Swamp out otherwise. Swamp out if load is 0MW during daytime.

Units behind it

UnitFuelMWWeightDirection
Orana BESSBattery4151.00charge
Orana BESSBattery4151.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
STUBO_SFLINE 7M12 Oct 2026 05:0012 Oct 2026 17:00COMPLETEHV equipt commissioning4
STUBO_SFLINE 7M13 Oct 2026 05:0013 Oct 2026 17:00COMPLETEHV equipt commissioning2
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.