NEM constraint causes, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Network as builtEquipment outageLimit on a single plant

By limit type

By cause

By region and cause

Constraint-hours by cause, per month

The 30 outages with the most binding hours

AreaSubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
Murraylink: SA to Victoria held at zeroMLRC, MLNK_BLINE ML_1, LINE DC_CONVERTER5 Nov 2026 01:004 Dec 2026 16:00PTPHV equipt maintenance479
Project EnergyConnect loop: N-3 outage constraint (dispatch and predispatch only)BURONGALINE 6G11 Aug 2026 12:004 Nov 2026 06:00COMPLETEHV equipt commissioning275
Project EnergyConnect loop: N-3 outage constraint (dispatch and predispatch only)BURONGALINE 6H11 Aug 2026 16:004 Nov 2026 06:00COMPLETEHV equipt commissioning275
Project EnergyConnect loop: N-3 outage constraint (dispatch and predispatch only)BURONGALINE 6C6 Oct 2026 14:004 Nov 2026 06:00COMPLETEHV equipt maintenance275
Haughton Solar Farm — system strength275KV_8859, H58_LARCLINE 275KV_885921 Sep 2026 07:002 Oct 2026 17:00COMPLETEHV equipt maintenance265
Haughton Solar Farm — system strengthH29_STAN, H24_CALVLINE 275KV_855, CB CPLR_5052, CB FDR_8552, CB 501214 Sep 2026 08:301 Oct 2026 18:00COMPLETEHV equipt commissioning250
Central Queensland: Gladstone corridor (Calliope River, Larcom Creek, Wurdong 275 kV)H8_BOYNE, 132KV_7146LINE 132KV_714614 Oct 2026 23:3024 Oct 2026 12:00COMPLETEHV equipt maintenance162
Central-west NSW: Molong–Orange North 132 kVORANGE_N, MOLONGLINE 94T28 Aug 2026 07:0016 Sep 2026 17:00COMPLETEHV equipt commissioning123
Out = Canberra-Capital (6) or Kangaroo Valley to Capital (3W), avoidCANBERRA, CAPITALLINE 630 Sep 2026 07:0019 Oct 2026 16:00COMPLETEHV equipt maintenance102
SA to NSW on PEC upper transfer limit of 0 MWBURONGALINE 6F11 Oct 2026 17:3015 Oct 2026 19:30COMPLETEHV equipt commissioning92
Snowy to NSW: transient stability limits (Yass–Bannaby–Marulan)STOCKDILLINE 115 Sep 2026 08:0027 Sep 2026 16:00COMPLETEHV equipt commissioning85
Out=PEC loop closed, one Bundey to Buronga (6C or 6F) 330 kV line O/S.6FLINE 6F16 Nov 2026 07:0020 Nov 2026 16:30COMPLETEHV equipt maintenance77
Aldoga Solar Farm — system strengthH20_BSND, H11_NEBOLINE 275KV_8846, CB FDR_88462, CB CPLR_5062, CB CPLR_50427 Sep 2026 07:0013 Sep 2026 11:30COMPLETEHV equipt commissioning76
SA to NSW on PEC upper transfer limit of 0 MWBURONGA, BALRANLDLINE X5/3, LINE X311 Oct 2026 17:3015 Oct 2026 01:30COMPLETEHV equipt commissioning76
SA to NSW on PEC upper transfer limit of 0 MWBURONGABUS B11 Oct 2026 17:3015 Oct 2026 01:30COMPLETEHV equipt commissioning76
Snowy to NSW: transient stability limits (Yass–Bannaby–Marulan)CAPITAL, CANBERRALINE 628 Oct 2026 06:0016 Nov 2026 16:00COMPLETEHV equipt maintenance73
Robertstown to North West Bend 1MW_3, MW_2LINE MW2MW3_12 Sep 2026 09:4513 Sep 2026 17:15COMPLETEHV equipt maintenance69
Kennedy Energy Park — system strengthH20_BSND, H170_GLNLINE 275KV_8720, CB FDR_87202, CB CPLR_5042, CB FDR_8719213 Sep 2026 12:0020 Sep 2026 17:00COMPLETEHV equipt commissioning55
Kennedy Energy Park — system strengthH11_NEBO, H170_GLNCB FDR_87202, CB FDR_88462, CB FDR_87192, CB CPLR_5022, LINE 275KV_8846N, CB CPLR_506213 Sep 2026 12:0020 Sep 2026 17:00COMPLETEHV equipt commissioning53
Remaining Davenport 132/ TX on NIL tripDAVENPCB CB6254, CB CB6257, TRANS T_1, CB CB654922 Sep 2026 08:0029 Sep 2026 07:00COMPLETEHV equipt maintenance45
Karadoc Solar Farm — system strengthWAGGA330, TUMUT3LINE 0515 Sep 2026 05:009 Sep 2026 18:00COMPLETEHV equipt commissioning45
Manage voltage collapse in northern SA for the trip of one 275kV lineBLYT_W, MUNN_PLINE BHWMUN_1, LINE BHWPAR_1, CB 80026 Nov 2026 08:0013 Nov 2026 16:00PTPHV equipt maintenance43
Robertstown to North West Bend 1MW_2, MW_3LINE MW2MW3_115 Sep 2026 09:4524 Sep 2026 14:45COMPLETEHV equipt maintenance40
Central Queensland: Gladstone corridor (Calliope River, Larcom Creek, Wurdong 275 kV)275KV_814/2, H6_GNGNCB FDR_8142, LINE 275KV_814/226 Oct 2026 10:0030 Oct 2026 17:00COMPLETEHV equipt maintenance37
Central Queensland: Gladstone corridor (Calliope River, Larcom Creek, Wurdong 275 kV)H58_LARC, 275KV_8859LINE 275KV_885926 Oct 2026 09:0030 Oct 2026 17:00COMPLETEHV equipt maintenance37
Central Queensland: Gladstone corridor (Calliope River, Larcom Creek, Wurdong 275 kV)H2_SPINE, H9_PLMWDLINE 275KV_80825 Aug 2026 07:002 Sep 2026 17:00COMPLETEHV equipt maintenance36
Hamilton Solar Farm — unit zeroT242_SPRTRANS X228 Sep 2026 12:302 Oct 2026 12:30COMPLETEHV equipt maintenance33
Hamilton Solar Farm — unit zeroT242_SPR, H35_STHMLINE 7457, LINE 132KV_7457, TRANS X128 Sep 2026 12:302 Oct 2026 12:30COMPLETEHV equipt maintenance33
Hamilton Solar Farm — unit zeroH35_STHM, T242_SPRTRANS X1, LINE 7457, LINE 132KV_7457, N/A N/A28 Sep 2026 13:002 Oct 2026 12:30COMPLETEHV equipt maintenance32
Hamilton Solar Farm — unit zeroH35_STHM, T242_SPRLINE 132KV_7457, LINE 7457, N/A N/A, TRANS X228 Sep 2026 13:002 Oct 2026 12:30COMPLETEHV equipt maintenance32
Each outage is listed once, against the area it affects most. Hours are for the whole outage.
Source: AEMO. Summary built 25 Nov 2026 02:26; data through 25 Nov 2026 01:25 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.