NEM Dashboard

ITK
Period

Lancaster Solar Farm — commissioning (zero MW)

VIC · Other · C_V_LANCSF1_ZERO
Most frequent constraint: Commissioning constraint for Lancaster Solar Farm of zero MW
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
13
% of period
0.6%
Network as built share
0.0%
Equipment outage share
97%
Single-plant limit share
2.5%
Units in constraints
1
MW in constraints
95
Curtailed while constrained
0.3 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
C_V_LANCSF1_04013Equipment outageOtherCommissioning / hold point constraint for Lancaster Solar Farm of 40 MW - HP2
NC_V_LANCSF10Limit on a single plantNon-ConformanceNon Conformance Constraint for LANCASTERSF1

Units behind it

UnitFuelMWWeightDirection
Lancaster Solar FarmSolar951.00discharge

Associated outages

No associated outage overlapped this period.
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.