NEM Dashboard

ITK
Period

Of 150 MW on Bundey

SA · Discretionary · I_6F_SN_150
Most frequent constraint: Discretionary limit of 150 MW on Bundey to Buronga (6F) 330 kV Line (SA to NSW)
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
46
% of period
2.1%
Network as built share
0.0%
Equipment outage share
0.7%
Single-plant limit share
99%
Units in constraints
17
MW in constraints
1,781
Curtailed while constrained
2.1 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
I_6F_SN_15046Limit on a single plantDiscretionaryDiscretionary limit of 150 MW on Bundey to Buronga (6F) 330 kV Line (SA to NSW)
S>>BDBU_RBTU_WEWT0Equipment outageThermalOut= Bundey to Buronga 330kV, avoid O/L Waterloo East-Waterloo 132kV line on trip of one Robertstown-Tungkillo 275kV line, Feedback

Units behind it

UnitFuelMWWeightDirection
Hallett GTOCGT2770.33discharge
Goyder South Wind Farm 1AWind2090.39discharge
Goyder South Wind Farm 1BWind2040.39discharge
Lake Bonney 2 Wind FarmWind1591.00charge
Hornsdale Power Reserve Unit 1Battery1500.30discharge
Hallett 4 North Brown HillWind1320.29discharge
Waterloo Wind FarmWind1311.00discharge
Willogoleche Wind FarmWind1200.30discharge
Hornsdale Wind Farm Stage 3Wind1120.30discharge
Templers BESSBattery1110.19charge
Hornsdale Wind Farm Stage 1Wind1020.30discharge
Hornsdale Wind Farm Stage 2Wind1020.30discharge
Snowtown Wind FarmWind990.63charge
Hallett Stage 1 Brown HillWind940.33discharge
Wattle PointWind910.71charge
Mintaro GTOCGT900.74charge
Lake Bonney 1 Wind FarmWind801.00charge
Hallett Stage 2 Hallett HillWind710.36discharge
SnuggeryOCGT631.00charge
Clements Gap BESSBattery600.21charge
Clements Gap Wind FarmWind570.45charge
Hallett 5 The Bluff WFWind520.29discharge
AngastonOther460.26charge
CanundaWind461.00charge
Ladbroke GroveOCGT400.92charge
Ladbroke GroveOCGT400.92charge
Lake Bonney 3 Wind FarmWind391.00charge
Dalrymple BESSBattery300.71charge
Lake Bonney Battery Energy StorageBattery251.00charge
Morgan To Whyalla Pipeline No 3 PSSolar80.60discharge
Morgan To Whyalla Pipeline No 1 PS And Water Filtration PlantSolar60.60discharge
Morgan To Whyalla Pipeline No 2 PSSolar60.60discharge
Morgan To Whyalla Pipeline No 4 PSSolar60.71discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
BURONGALINE 6F29 Sep 2026 07:001 Oct 2026 12:00COMPLETEHV equipt commissioning0
Source: AEMO. Summary built 25 Nov 2026 02:56; data through 25 Nov 2026 01:55 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.