Out=PEC loop closed, one Bundey to Buronga (6C or 6F) 330 kV line O/S.
NSW · Other · L_PEC_BDBU
Most frequent constraint: Out=PEC loop closed, one Bundey to Buronga (6C or 6F) 330 kV line O/S. Loop flow constraint. Feedback
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
78
% of period
3.6%
Network as built share
0.0%
Equipment outage share
100%
Single-plant limit share
0.0%
Units in constraints
0
MW in constraints
0
Curtailed while constrained
0.0 GWh
Value of that curtailment
$0.0m
Network as built: the limit binds with every line and transformer in service. AEMO marks these “Out = Nil”.
Equipment outage: the limit applies only while a named line or transformer is out of service.
Limit on a single plant: AEMO caps one wind or solar farm. Most are system strength limits, which depend on how many coal, gas or hydro units and synchronous condensers are running nearby.
Constraint-hours by cause, per month
Network as builtEquipment outageLimit on a single plant
Constraints that bound in the period
Constraint
Hours
Cause
Limit type
AEMO description
L_PEC_BDBU
78
Equipment outage
Other
Out=PEC loop closed, one Bundey to Buronga (6C or 6F) 330 kV line O/S. Loop flow constraint. Feedback
Units behind it
No units recorded for this area.
Associated outages
Substation
Equipment
Start
End
Status
Reason
Binding hours (whole outage)
6F
LINE 6F
16 Nov 2026 07:00
20 Nov 2026 16:30
COMPLETE
HV equipt maintenance
77
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.