Most frequent constraint: Out=PEC loop closed, NIL major outages around PEC loop. Feedback.
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
419
% of period
19%
Network as built share
100%
Equipment outage share
0.0%
Single-plant limit share
0.0%
Units in constraints
0
MW in constraints
0
Curtailed while constrained
0.0 GWh
Value of that curtailment
$0.0m
Network as built: the limit binds with every line and transformer in service. AEMO marks these “Out = Nil”.
Equipment outage: the limit applies only while a named line or transformer is out of service.
Limit on a single plant: AEMO caps one wind or solar farm. Most are system strength limits, which depend on how many coal, gas or hydro units and synchronous condensers are running nearby.
Constraint-hours by cause, per month
Network as builtEquipment outageLimit on a single plant
Constraints that bound in the period
Constraint
Hours
Cause
Limit type
AEMO description
L_PEC_NIL
419
Network as built
Other
Out=PEC loop closed, NIL major outages around PEC loop. Feedback.
Units behind it
No units recorded for this area.
Associated outages
No associated outage overlapped this period.
Source: AEMO. Summary built 25 Nov 2026 02:26; data through 25 Nov 2026 01:25 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.