Project EnergyConnect loop: N-3 outage constraint (dispatch and predispatch only)

NSW · Other · L_PEC_X_6C_6G_6H_XST
Most frequent constraint: Out=PEC loop closed, N-3 outages around PEC loop, 6C or 6F line plus 330 kV connection between Wagga and Buronga open. No ST Formulation, DS and PD Only. Feedback.
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
275
% of period
13%
Network as built share
0.0%
Equipment outage share
100%
Single-plant limit share
0.0%
Units in constraints
0
MW in constraints
0
Curtailed while constrained
0.0 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
L_PEC_X_6C_6G_6H_XST275Equipment outageOtherOut=PEC loop closed, N-3 outages around PEC loop, 6C or 6F line plus 330 kV connection between Wagga and Buronga open. No ST Formulation, DS and PD Only. Feedback.

Units behind it

No units recorded for this area.

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
BURONGALINE 6G11 Aug 2026 12:004 Nov 2026 06:00COMPLETEHV equipt commissioning275
BURONGALINE 6H11 Aug 2026 16:004 Nov 2026 06:00COMPLETEHV equipt commissioning275
BURONGALINE 6C6 Oct 2026 14:004 Nov 2026 06:00COMPLETEHV equipt maintenance275
Source: AEMO. Summary built 25 Nov 2026 02:26; data through 25 Nov 2026 01:25 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.