NSW mid-north coast: Port Macquarie–Herons Creek 132 kV

NSW · Thermal · N>>NIL_964_84_S
Most frequent constraint: Out= NIL, avoid O/L Port Macquarie to Herons Creek Tee (964/2) on trip of Tamworth to Liddell (84) line, Feedback
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
339
% of period
16%
Network as built share
96%
Equipment outage share
4.4%
Single-plant limit share
0.0%
Units in constraints
10
MW in constraints
1,366
Curtailed while constrained
1.9 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
N>>NIL_964_84_S259Network as builtThermalOut= NIL, avoid O/L Port Macquarie to Herons Creek Tee (964/2) on trip of Tamworth to Liddell (84) line, Feedback
N>>NIL_85_86_S60Network as builtThermalOut= NIL, avoid O/L Uralla to Tamworth (85) on trip of Armidale to Tamworth (86) line, Feedback
N>>NIL_86_85_S15Network as builtThermalOut= NIL, avoid O/L Armidale to Tamworth (86) on trip of Uralla to Tamworth (85) line, Feedback
N>>965_9W2_9W86Equipment outageThermalOut= Armidale to Kempsey (965), avoid O/L Raliegh to Kempsey 132kV line on trip of Coffs Harbour to Boambee (9W8) 132kV line, Feedback
N>>9W7_9W2_9655Equipment outageThermalOut= One of Coffs Harbour to Kempsey (9W5 or 9W6 or 9W7 or 9W8), avoid O/L Raliegh to Kempsey (9W2) 132kV line on trip of Armidale to Kempsey (965) 132kV line, Feedback
N>>86_85_NIL_S3Network as builtThermalOut= Tamworth-Armidale(86), avoid O/L Uralla to Tamworth (85) 330kV line on trip of Nil, Feedback [Note: Assumed Armidale-Moree-Tamworth parrellel open (96M OPEN),Armidale-Kempsey-Newcastle 132kV parrallel open (964 OPEN)]
N>>81_964_823Equipment outageThermalOut = Liddell to Newcastle (81) line, avoid O/L Port Macquarie to Herron Creek Tee (964/2) on trip of Liddell to Tomago (82) line, (Note: Swamps if 964 O/S)
N>>NIL_8U_86_S2Network as builtThermalOut= NIL, avoid O/L Armidale to Uralla (8U) on trip of Armidale to Tamworth (86) line, Feedback
N>>964_85_86_S0Equipment outageThermalOut= Taree to Port Macquarie (964) 132kV line, avoid O/L Uralla to Tamworth (85) on trip of Armidale to Tamworth (86) line, Feedback
N>>NIL_86_NIL_S0Network as builtThermalOut= NIL, avoid O/L Armidale to Tamworth (86) on trip of Nil, Feedback
N>>81_964_840Equipment outageThermalOut = Liddell to Newcastle (81) line, avoid O/L Port Macquarie to Herron Creek Tee (964/2) on trip of Liddell to Tamworth (84) line,(Note: Swamps if 964 O/S)
N>>85_86_NIL_S0Network as builtThermalOut = Uralla to Tamworth (85) line, avoid O/L Armidale to Tamworth (86) on trip of Nil, [Note: Assumed Armidale-Moree-Tamworth parrellel open (96M OPEN),Armidale-Kempsey-Newcastle 132kV parrallel open (964 OPEN)]
N>>NIL_964_88_S0Network as builtThermalOut= NIL, avoid O/L Port Macquarie to Herons Creek Tee (964/2) on trip of Tamworth to Muswellbrook (88) line, Feedback
N>>86_8U_NIL_S0Network as builtThermalOut= Tamworth-Armidale(86), avoid O/L Armidale to Uralla (8U) on trip of Nil, [Note: Assumed Armidale-Moree-Tamworth parrellel open (96M OPEN),Armidale-Kempsey-Newcastle 132kV parrallel open (964 OPEN)]

Units behind it

UnitFuelMWWeightDirection
BayswaterCoal6850.18discharge
BayswaterCoal6850.18discharge
BayswaterCoal6850.22discharge
BayswaterCoal6600.22discharge
Liddell BESSBattery5000.23discharge
Hunter Power StationOCGT3750.22charge
Hunter Power StationOCGT3750.22charge
Sapphire Wind FarmWind2701.00discharge
Sapphire Wind FarmWind2701.00charge
New England Solar FarmSolar2001.00discharge
New England Solar FarmSolar2001.00discharge
White Rock Wind Farm - Stage 1Wind1751.00discharge
White Rock Wind Farm - Stage 1Wind1751.00charge
Metz Solar FarmSolar1351.00discharge
Metz Solar FarmSolar1351.00charge
Gunnedah Solar FarmSolar1101.00discharge
Gunnedah Solar FarmSolar1101.00charge
New England BESSBattery1001.00discharge
New England BESSBattery1001.00discharge
Moree Solar FarmSolar561.00discharge
Moree Solar FarmSolar561.00charge
Hunter EconomicZoneOther210.22charge
White Rock Solar FarmSolar201.00charge
White Rock Solar FarmSolar201.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
ARMIDALE, KEMPSEYLINE 96523 Nov 2026 06:3025 Nov 2026 16:00PTPHV equipt maintenance6
COFFS, BOAMBEELINE 9W810 Oct 2026 06:0010 Oct 2026 13:00COMPLETEHV equipt maintenance5
NEWCSTLE, LIDDELLLINE 8123 Sep 2026 08:0023 Sep 2026 17:00COMPLETEHV equipt maintenance3
TAMWORTH, ARMIDALELINE 864 Nov 2026 06:304 Nov 2026 16:00COMPLETEHV equipt maintenance1
TAMWORTH, ARMIDALELINE 865 Nov 2026 06:305 Nov 2026 15:00COMPLETEHV equipt maintenance1
TAREE, PT_MCQARLINE 96427 Oct 2026 06:1528 Oct 2026 15:30COMPLETEHV equipt maintenance0
ARMIDALE, TAMWORTHLINE 8615 Oct 2026 06:3015 Oct 2026 16:00COMPLETEHV equipt maintenance0
TAMWORTHLINE 8513 Nov 2026 06:3013 Nov 2026 15:00MTLTPHV equipt maintenance0
TAMWORTH, ARMIDALELINE 8616 Oct 2026 06:3016 Oct 2026 16:00COMPLETEHV equipt maintenance0
ARMIDALE, TAMWORTHLINE 8612 Oct 2026 06:3012 Oct 2026 16:00COMPLETEHV equipt maintenance0
TAMWORTHBUS 51230 Sep 2026 07:0030 Sep 2026 17:00COMPLETEHV equipt commissioning0
TAMWORTH, ARMIDALELINE 8614 Oct 2026 06:3014 Oct 2026 17:00COMPLETEHV equipt maintenance0
ARMIDALE, TAMWORTHLINE 863 Nov 2026 06:303 Nov 2026 15:00COMPLETEHV equipt maintenance0
TAMWORTH, ARMIDALELINE 867 Nov 2026 06:307 Nov 2026 15:00COMPLETEHV equipt maintenance0
Source: AEMO. Summary built 25 Nov 2026 02:26; data through 25 Nov 2026 01:25 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.