Most frequent constraint: Out= Nil, avoid O/L of one Canberra to Queanbeyan (977/1 or 976/1) 132kV line on trip of other Canberra to Queanbeyan (977/1 or 976/1) 132kV line, Feedback
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
23
% of period
1.1%
Network as built share
99%
Equipment outage share
0.0%
Single-plant limit share
1.5%
Units in constraints
2
MW in constraints
110
Curtailed while constrained
0.0 GWh
Value of that curtailment
$0.0m
Network as built: the limit binds with every line and transformer in service. AEMO marks these “Out = Nil”.
Equipment outage: the limit applies only while a named line or transformer is out of service.
Limit on a single plant: AEMO caps one wind or solar farm. Most are system strength limits, which depend on how many coal, gas or hydro units and synchronous condensers are running nearby.
Constraint-hours by cause, per month
Network as builtEquipment outageLimit on a single plant
Constraints that bound in the period
Constraint
Hours
Cause
Limit type
AEMO description
N>NIL_977_976
22
Network as built
Thermal
Out= Nil, avoid O/L of one Canberra to Queanbeyan (977/1 or 976/1) 132kV line on trip of other Canberra to Queanbeyan (977/1 or 976/1) 132kV line, Feedback
NC_N_QBYNB1
0
Limit on a single plant
Non-Conformance
Non Conformance Constraint for QBYN BESS
N>976_977_NIL_2
0
Network as built
Thermal
Out= Canberra to Queanbeyan (976/1 or 977/1) 132kV line, avoid O/L Queanbeyan to Canberra (976/3 or 977/1) on trip of Nil, Feedback
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.