Narrandera to Uranquinty (99F)

NSW · Thermal · N>NIL_99F
Most frequent constraint: Out= Nil, avoid O/L Narrandera to Uranquinty (99F) 132 kV line on trip of Nil, Feedback
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
85
% of period
4.0%
Network as built share
100%
Equipment outage share
0.0%
Single-plant limit share
0.0%
Units in constraints
8
MW in constraints
1,102
Curtailed while constrained
0.0 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
N>NIL_99F59Network as builtThermalOut= Nil, avoid O/L Narrandera to Uranquinty (99F) 132 kV line on trip of Nil, Feedback
N>DPTX1-2_TX_NIL28Network as builtThermalOut= one Darlington Pt 132/330kV TX1 or TX2, avoid O/L remaining Darlington Pt 132/330kV TX on trip of Nil, Feedback

Units behind it

UnitFuelMWWeightDirection
Darlington Point Solar FarmSolar2751.00discharge
Avonlie Solar FarmSolar2541.00discharge
UranquintyOCGT1730.12discharge
UranquintyOCGT1730.28charge
UranquintyOCGT1730.28charge
UranquintyOCGT1730.28charge
UranquintyOCGT1730.28charge
UranquintyOCGT1730.12discharge
UranquintyOCGT1730.12discharge
UranquintyOCGT1730.12discharge
Finley Solar FarmSolar1621.00discharge
Coleambally Solar FarmSolar1500.96discharge
Bomen Solar FarmSolar1210.07discharge
Hillston Sun FarmSolar1101.00discharge
West Wyalong Solar FarmSolar1050.07discharge
Sebastopol Solar FarmSolar900.07discharge
Riverina Energy Storage System 2Battery651.00discharge
Wyalong Solar FarmSolar620.07discharge
Riverina Energy Storage System 1Battery601.00discharge
Wagga North Solar FarmSolar560.07discharge
Junee Solar FarmSolar360.07discharge
Corowa Solar FarmSolar360.15discharge
Corowa Solar FarmSolar360.82charge
Hume Dam NSWWater290.28charge
Darlington Point Energy Storage SystemBattery251.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
DARL_PTTRANS 2H15 Sep 2026 08:0018 Sep 2026 16:00COMPLETEHV equipt maintenance16
DARL_PTTRANS 2H17 Nov 2026 07:0017 Nov 2026 15:00COMPLETEHV equipt maintenance7
DARL_PTTRANS 1H8 Sep 2026 08:0011 Sep 2026 15:00COMPLETEHV equipt maintenance5
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.