NEM Dashboard

ITK
Period

Mulwala 1 or 2 22/ transformer

NSW · Thermal · N>NIL_MLTX_LV
Most frequent constraint: Out= Nil, avoid O/L Mulwala #1 or #2 22/132kV transformer on trip of Nil, Feedback. 90% of Rating is used as operating margin.
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
80
% of period
3.7%
Network as built share
95%
Equipment outage share
0.0%
Single-plant limit share
5.3%
Units in constraints
1
MW in constraints
31
Curtailed while constrained
0.1 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
N>NIL_MLTX_LV76Network as builtThermalOut= Nil, avoid O/L Mulwala #1 or #2 22/132kV transformer on trip of Nil, Feedback. 90% of Rating is used as operating margin.
N_MULWASF1_ZERO4Limit on a single plantUnit ZeroMulwala Solar Farm upper limit of 0 MW

Units behind it

UnitFuelMWWeightDirection
Mulwala Solar FarmSolar311.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
MULWALACB 8B525 Oct 2026 15:081 Nov 2026 17:00COMPLETEHV equipt maintenance4
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.