Coleambally Solar Farm — system strength

NSW · System Strength · N_COLEASF1_FLT_50
Most frequent constraint: Limit Coleambally solar farm upper limit to 50 MW to manage post contingent voltage oscillation
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
39
% of period
1.8%
Network as built share
0.0%
Equipment outage share
0.0%
Single-plant limit share
100%
Units in constraints
1
MW in constraints
150
Curtailed while constrained
0.9 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
N_COLEASF1_FLT_5020Limit on a single plantSystem StrengthLimit Coleambally solar farm upper limit to 50 MW to manage post contingent voltage oscillation
N_COLEASF1_FLT_4019Limit on a single plantSystem StrengthLimit Coleambally solar farm upper limit to 40 MW to manage post contingent voltage oscillation

Units behind it

UnitFuelMWWeightDirection
Coleambally Solar FarmSolar1501.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
BURONGA, BALRANLDLINE X3, LINE X5/313 Sep 2026 05:0015 Sep 2026 19:00COMPLETEHV equipt commissioning12
BALRANLD, BURONGALINE X3, LINE X5/311 Oct 2026 17:3015 Oct 2026 01:30COMPLETEHV equipt commissioning9
BURONGABUS B11 Oct 2026 17:3015 Oct 2026 01:30COMPLETEHV equipt commissioning9
BURONGALINE 6F11 Oct 2026 17:3015 Oct 2026 19:30COMPLETEHV equipt commissioning9
RCTSBUS 7MN2, CB 1CAP_1B_66, LINE CPTS_RCTS_220, LINE X9, CB 2CAP_2B_66, CAP 2CAP_22021 Sep 2026 06:0021 Sep 2026 19:00COMPLETEHV equipt maintenance5
RCTSBUS 7MN2, CAP 2CAP_220, LINE X9, LINE CPTS_RCTS_22016 Oct 2026 05:0016 Oct 2026 18:00COMPLETEHV equipt maintenance5
BURONGALINE 6F16 Oct 2026 05:0016 Oct 2026 18:00COMPLETEHV equipt commissioning5
RCTSCB 2CAP_2B_66, LINE X9, CAP 2CAP_220, LINE CPTS_RCTS_220, CB 1CAP_1B_66, BUS 7MN222 Sep 2026 06:0022 Sep 2026 19:00COMPLETEHV equipt maintenance5
RCTSLINE X9, CAP 2CAP_220, LINE CPTS_RCTS_220, BUS 7MN215 Oct 2026 06:3015 Oct 2026 19:30COMPLETEHV equipt maintenance4
S_EAST, HYTSLINE HYTS_SESS2_27515 Oct 2026 07:0015 Oct 2026 16:00COMPLETEHV equipt maintenance4
S_EAST, HYTSTRANS M1TR, LINE HYTS_SESS1_27514 Oct 2026 07:0014 Oct 2026 16:00COMPLETEHV equipt maintenance3
BURONGABUS B15 Sep 2026 13:0015 Sep 2026 19:00COMPLETEHV equipt commissioning2
BURONGABUS B13 Sep 2026 05:0013 Sep 2026 11:00COMPLETEHV equipt commissioning1
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.