Darlington Point Solar Farm + Hillston Sun Farm — system strength

NSW · System Strength · N_DARLSF_FLT_100
Most frequent constraint: Limit Darlington Pt Solar Farm upper limit to 100 MW to manage post contingent voltage oscillation
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
84
% of period
3.9%
Network as built share
0.0%
Equipment outage share
0.0%
Single-plant limit share
100%
Units in constraints
2
MW in constraints
385
Curtailed while constrained
2.7 GWh
Value of that curtailment
$0.1m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
N_DARLSF_FLT_10045Limit on a single plantSystem StrengthLimit Darlington Pt Solar Farm upper limit to 100 MW to manage post contingent voltage oscillation
N_DARLSF_FLT_6539Limit on a single plantSystem StrengthLimit Darlington Pt Solar Farm upper limit to 65 MW to manage post contingent voltage oscillation

Units behind it

UnitFuelMWWeightDirection
Darlington Point Solar FarmSolar2751.00discharge
Hillston Sun FarmSolar1101.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
BALRANLD, BURONGALINE X3, LINE X5/313 Sep 2026 05:0015 Sep 2026 19:00COMPLETEHV equipt commissioning23
BALRANLD, BURONGALINE X3, LINE X5/311 Oct 2026 17:3015 Oct 2026 01:30COMPLETEHV equipt commissioning21
BURONGABUS B11 Oct 2026 17:3015 Oct 2026 01:30COMPLETEHV equipt commissioning21
BURONGALINE 6F11 Oct 2026 17:3015 Oct 2026 19:30COMPLETEHV equipt commissioning21
RCTSLINE CPTS_RCTS_220, BUS 7MN2, CB 1CAP_1B_66, LINE X9, CB 2CAP_2B_66, CAP 2CAP_22021 Sep 2026 06:0021 Sep 2026 19:00COMPLETEHV equipt maintenance10
RCTSLINE X9, CB 2CAP_2B_66, CAP 2CAP_220, LINE CPTS_RCTS_220, CB 1CAP_1B_66, BUS 7MN222 Sep 2026 06:0022 Sep 2026 19:00COMPLETEHV equipt maintenance10
RCTSLINE X9, CAP 2CAP_220, LINE CPTS_RCTS_220, BUS 7MN215 Oct 2026 06:3015 Oct 2026 19:30COMPLETEHV equipt maintenance10
S_EAST, HYTSTRANS M1TR, LINE HYTS_SESS1_27514 Oct 2026 07:0014 Oct 2026 16:00COMPLETEHV equipt maintenance9
RCTSLINE X9, CAP 2CAP_220, BUS 7MN2, LINE CPTS_RCTS_22016 Oct 2026 05:0016 Oct 2026 18:00COMPLETEHV equipt maintenance9
BURONGALINE 6F16 Oct 2026 05:0016 Oct 2026 18:00COMPLETEHV equipt commissioning9
S_EAST, HYTSLINE HYTS_SESS2_27515 Oct 2026 07:0015 Oct 2026 16:00COMPLETEHV equipt maintenance8
BURONGABUS B13 Sep 2026 05:0013 Sep 2026 11:00COMPLETEHV equipt commissioning3
BURONGABUS B15 Sep 2026 13:0015 Sep 2026 19:00COMPLETEHV equipt commissioning3
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.