Darlington Point Solar Farm + Hillston Sun Farm — system strength
NSW · System Strength · N_DARLSF_FLT_100
Most frequent constraint: Limit Darlington Pt Solar Farm upper limit to 100 MW to manage post contingent voltage oscillation
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
84
% of period
3.9%
Network as built share
0.0%
Equipment outage share
0.0%
Single-plant limit share
100%
Units in constraints
2
MW in constraints
385
Curtailed while constrained
2.7 GWh
Value of that curtailment
$0.1m
Network as built: the limit binds with every line and transformer in service. AEMO marks these “Out = Nil”.
Equipment outage: the limit applies only while a named line or transformer is out of service.
Limit on a single plant: AEMO caps one wind or solar farm. Most are system strength limits, which depend on how many coal, gas or hydro units and synchronous condensers are running nearby.
Constraint-hours by cause, per month
Network as builtEquipment outageLimit on a single plant
Constraints that bound in the period
Constraint
Hours
Cause
Limit type
AEMO description
N_DARLSF_FLT_100
45
Limit on a single plant
System Strength
Limit Darlington Pt Solar Farm upper limit to 100 MW to manage post contingent voltage oscillation
N_DARLSF_FLT_65
39
Limit on a single plant
System Strength
Limit Darlington Pt Solar Farm upper limit to 65 MW to manage post contingent voltage oscillation
LINE CPTS_RCTS_220, BUS 7MN2, CB 1CAP_1B_66, LINE X9, CB 2CAP_2B_66, CAP 2CAP_220
21 Sep 2026 06:00
21 Sep 2026 19:00
COMPLETE
HV equipt maintenance
10
RCTS
LINE X9, CB 2CAP_2B_66, CAP 2CAP_220, LINE CPTS_RCTS_220, CB 1CAP_1B_66, BUS 7MN2
22 Sep 2026 06:00
22 Sep 2026 19:00
COMPLETE
HV equipt maintenance
10
RCTS
LINE X9, CAP 2CAP_220, LINE CPTS_RCTS_220, BUS 7MN2
15 Oct 2026 06:30
15 Oct 2026 19:30
COMPLETE
HV equipt maintenance
10
S_EAST, HYTS
TRANS M1TR, LINE HYTS_SESS1_275
14 Oct 2026 07:00
14 Oct 2026 16:00
COMPLETE
HV equipt maintenance
9
RCTS
LINE X9, CAP 2CAP_220, BUS 7MN2, LINE CPTS_RCTS_220
16 Oct 2026 05:00
16 Oct 2026 18:00
COMPLETE
HV equipt maintenance
9
BURONGA
LINE 6F
16 Oct 2026 05:00
16 Oct 2026 18:00
COMPLETE
HV equipt commissioning
9
S_EAST, HYTS
LINE HYTS_SESS2_275
15 Oct 2026 07:00
15 Oct 2026 16:00
COMPLETE
HV equipt maintenance
8
BURONGA
BUS B
13 Sep 2026 05:00
13 Sep 2026 11:00
COMPLETE
HV equipt commissioning
3
BURONGA
BUS B
15 Sep 2026 13:00
15 Sep 2026 19:00
COMPLETE
HV equipt commissioning
3
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.