Most frequent constraint: Limit Finley solar farm upper limit to 93 MW to manage post contingent voltage oscillation
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
23
% of period
1.1%
Network as built share
0.0%
Equipment outage share
1.4%
Single-plant limit share
99%
Units in constraints
1
MW in constraints
162
Curtailed while constrained
0.1 GWh
Value of that curtailment
$0.0m
Network as built: the limit binds with every line and transformer in service. AEMO marks these “Out = Nil”.
Equipment outage: the limit applies only while a named line or transformer is out of service.
Limit on a single plant: AEMO caps one wind or solar farm. Most are system strength limits, which depend on how many coal, gas or hydro units and synchronous condensers are running nearby.
Constraint-hours by cause, per month
Network as builtEquipment outageLimit on a single plant
Constraints that bound in the period
Constraint
Hours
Cause
Limit type
AEMO description
N_FINLYSF_FLT_40
22
Limit on a single plant
System Strength
Limit Finley solar farm upper limit to 40 MW to manage post contingent voltage oscillation
N_FINLEYSF_49_INV
1
Limit on a single plant
System Strength
Finley Solar Farm inverter limit of 49. Constraint to violate if Finley Solar Farm inverter availability greater than 49. Swamp out otherwise. DS only
N_FINLYSF1_0INV
0
Equipment outage
Other
Finley Solar Farm inverter limit of zero. Constraint to violate if Finley Solar Farm inverter availability greater than zero. Swamp out otherwise. DS only
N_FINLEYSF_31_INV
0
Limit on a single plant
System Strength
Finley Solar Farm inverter limit of 31. Constraint to violate if Finley Solar Farm inverter availability greater than 31. Swamp out otherwise. DS only
N_FINLEYSF_CAP_66
0
Limit on a single plant
System Strength
MW conversion for Finley Solar Farm inverter limit of 49.
BUS 7MN2, CB 1CAP_1B_66, LINE CPTS_RCTS_220, CB 2CAP_2B_66, LINE X9, CAP 2CAP_220
21 Sep 2026 06:00
21 Sep 2026 19:00
COMPLETE
HV equipt maintenance
9
RCTS
LINE CPTS_RCTS_220, CB 2CAP_2B_66, LINE X9, CAP 2CAP_220, BUS 7MN2, CB 1CAP_1B_66
22 Sep 2026 06:00
22 Sep 2026 19:00
COMPLETE
HV equipt maintenance
9
RCTS
BUS 7MN2, LINE X9, CAP 2CAP_220, LINE CPTS_RCTS_220
16 Oct 2026 05:00
16 Oct 2026 18:00
COMPLETE
HV equipt maintenance
3
BURONGA
LINE 6F
16 Oct 2026 05:00
16 Oct 2026 18:00
COMPLETE
HV equipt commissioning
3
BURONGA
SYNC SCON1, SYNC 1
9 Jan 2026 16:46
31 Dec 2026 22:00
PTP
HV equipt maintenance
2
–
N/A N/A
15 Sep 2026 07:00
15 Sep 2026 17:00
MTLTP
HV equipt commissioning
1
BURONGA
SYNC SCON5
12 Sep 2026 16:00
13 Sep 2026 17:00
COMPLETE
HV equipt commissioning
1
–
N/A N/A
27 Oct 2026 06:00
29 Oct 2026 16:00
COMPLETE
HV equipt commissioning
0
JINDERA, WOTS
LINE 060, LINE N/A
28 Oct 2026 06:00
28 Oct 2026 17:00
COMPLETE
HV equipt maintenance
0
WOTS, JINDERA
LINE 060
28 Oct 2026 06:00
28 Oct 2026 17:00
COMPLETE
HV equipt maintenance
0
BURONGA
LINE 6F
28 Oct 2026 06:00
28 Oct 2026 17:00
COMPLETE
HV equipt commissioning
0
MULWALA
CB 7B1
28 Oct 2026 06:00
28 Oct 2026 17:00
COMPLETE
HV equipt maintenance
0
WAGGA330
BUS 4B1
8 Oct 2026 07:00
8 Oct 2026 16:00
COMPLETE
HV equipt maintenance
0
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.