Finley Solar Farm — system strength

NSW · System Strength · N_FINLYSF_FLT_93
Most frequent constraint: Limit Finley solar farm upper limit to 93 MW to manage post contingent voltage oscillation
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
23
% of period
1.1%
Network as built share
0.0%
Equipment outage share
1.4%
Single-plant limit share
99%
Units in constraints
1
MW in constraints
162
Curtailed while constrained
0.1 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
N_FINLYSF_FLT_4022Limit on a single plantSystem StrengthLimit Finley solar farm upper limit to 40 MW to manage post contingent voltage oscillation
N_FINLEYSF_49_INV1Limit on a single plantSystem StrengthFinley Solar Farm inverter limit of 49. Constraint to violate if Finley Solar Farm inverter availability greater than 49. Swamp out otherwise. DS only
N_FINLYSF1_0INV0Equipment outageOtherFinley Solar Farm inverter limit of zero. Constraint to violate if Finley Solar Farm inverter availability greater than zero. Swamp out otherwise. DS only
N_FINLEYSF_31_INV0Limit on a single plantSystem StrengthFinley Solar Farm inverter limit of 31. Constraint to violate if Finley Solar Farm inverter availability greater than 31. Swamp out otherwise. DS only
N_FINLEYSF_CAP_660Limit on a single plantSystem StrengthMW conversion for Finley Solar Farm inverter limit of 49.

Units behind it

UnitFuelMWWeightDirection
Finley Solar FarmSolar1621.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
RCTSBUS 7MN2, CB 1CAP_1B_66, LINE CPTS_RCTS_220, CB 2CAP_2B_66, LINE X9, CAP 2CAP_22021 Sep 2026 06:0021 Sep 2026 19:00COMPLETEHV equipt maintenance9
RCTSLINE CPTS_RCTS_220, CB 2CAP_2B_66, LINE X9, CAP 2CAP_220, BUS 7MN2, CB 1CAP_1B_6622 Sep 2026 06:0022 Sep 2026 19:00COMPLETEHV equipt maintenance9
RCTSBUS 7MN2, LINE X9, CAP 2CAP_220, LINE CPTS_RCTS_22016 Oct 2026 05:0016 Oct 2026 18:00COMPLETEHV equipt maintenance3
BURONGALINE 6F16 Oct 2026 05:0016 Oct 2026 18:00COMPLETEHV equipt commissioning3
BURONGASYNC SCON1, SYNC 19 Jan 2026 16:4631 Dec 2026 22:00PTPHV equipt maintenance2
–N/A N/A15 Sep 2026 07:0015 Sep 2026 17:00MTLTPHV equipt commissioning1
BURONGASYNC SCON512 Sep 2026 16:0013 Sep 2026 17:00COMPLETEHV equipt commissioning1
–N/A N/A27 Oct 2026 06:0029 Oct 2026 16:00COMPLETEHV equipt commissioning0
JINDERA, WOTSLINE 060, LINE N/A28 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance0
WOTS, JINDERALINE 06028 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance0
BURONGALINE 6F28 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt commissioning0
MULWALACB 7B128 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance0
WAGGA330BUS 4B18 Oct 2026 07:008 Oct 2026 16:00COMPLETEHV equipt maintenance0
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.