Limondale Solar Farm — system strength

NSW · System Strength · N_LIMOSF2_FLT_15
Most frequent constraint: Limit Limondale 2 solar farm upper limit to 15 MW to manage post contingent voltage oscillation
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
58
% of period
2.7%
Network as built share
0.0%
Equipment outage share
0.4%
Single-plant limit share
100%
Units in constraints
1
MW in constraints
29
Curtailed while constrained
0.4 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
N_LIMOSF2_FLT_1038Limit on a single plantSystem StrengthLimit Limondale 2 solar farm upper limit to 10 MW to manage post contingent voltage oscillation
N_LIMOSF21_CAP_2318Limit on a single plantSystem StrengthMW conversion for Limondale Solar Farm 2 limit of 11.
N_LIMOSF2_FLT_152Limit on a single plantSystem StrengthLimit Limondale 2 solar farm upper limit to 15 MW to manage post contingent voltage oscillation
N_LIMOSF21_0INV0Equipment outageOtherLimondale 2 Solar Farm inverter limit of zero. Constraint to violate if Limondale 2 Solar Farm inverter availability greater than zero. Swamp out otherwise. DS only
N_LIMOSF21_11_INV0Limit on a single plantSystem StrengthLimondale 2 Solar Farm inverter limit of 11. Constraint to violate if Limondale 2 Solar Farm inverter availability greater than 11. Swamp out otherwise. DS only

Units behind it

UnitFuelMWWeightDirection
Limondale Solar Farm 2Solar291.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
TUMUT3, WAGGA330LINE 0515 Sep 2026 05:009 Sep 2026 18:00COMPLETEHV equipt commissioning18
RCTSLINE CPTS_RCTS_220, CB 2CAP_2B_66, LINE X9, BUS 7MN2, CB 1CAP_1B_66, CAP 2CAP_22021 Sep 2026 06:0021 Sep 2026 19:00COMPLETEHV equipt maintenance10
RCTSLINE CPTS_RCTS_220, CB 1CAP_1B_66, BUS 7MN2, CAP 2CAP_220, LINE X9, CB 2CAP_2B_6622 Sep 2026 06:0022 Sep 2026 19:00COMPLETEHV equipt maintenance10
RCTSLINE X9, CAP 2CAP_220, BUS 7MN2, LINE CPTS_RCTS_22016 Oct 2026 05:0016 Oct 2026 18:00COMPLETEHV equipt maintenance8
BURONGALINE 6F16 Oct 2026 05:0016 Oct 2026 18:00COMPLETEHV equipt commissioning8
RCTSLINE CPTS_RCTS_220, BUS 7MN2, CAP 2CAP_220, LINE X915 Oct 2026 06:3015 Oct 2026 19:30COMPLETEHV equipt maintenance8
S_EAST, HYTSLINE HYTS_SESS2_27515 Oct 2026 07:0015 Oct 2026 16:00COMPLETEHV equipt maintenance7
KANGAROO, DAPTOLINE 185 Sep 2026 08:006 Sep 2026 17:00COMPLETEHV equipt maintenance4
SHTS, BETSLINE BETS_SHTS_22012 Oct 2026 11:0023 Oct 2026 17:00COMPLETEHV equipt maintenance2
–N/A N/A27 Oct 2026 06:0029 Oct 2026 16:00COMPLETEHV equipt commissioning0
WOTS, JINDERALINE N/A, LINE 06028 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance0
JINDERA, WOTSLINE 06028 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance0
BURONGALINE 6F28 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt commissioning0
MULWALACB 7B128 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance0
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.