Most frequent constraint: Limit Limondale 2 solar farm upper limit to 15 MW to manage post contingent voltage oscillation
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
58
% of period
2.7%
Network as built share
0.0%
Equipment outage share
0.4%
Single-plant limit share
100%
Units in constraints
1
MW in constraints
29
Curtailed while constrained
0.4 GWh
Value of that curtailment
$0.0m
Network as built: the limit binds with every line and transformer in service. AEMO marks these “Out = Nil”.
Equipment outage: the limit applies only while a named line or transformer is out of service.
Limit on a single plant: AEMO caps one wind or solar farm. Most are system strength limits, which depend on how many coal, gas or hydro units and synchronous condensers are running nearby.
Constraint-hours by cause, per month
Network as builtEquipment outageLimit on a single plant
Constraints that bound in the period
Constraint
Hours
Cause
Limit type
AEMO description
N_LIMOSF2_FLT_10
38
Limit on a single plant
System Strength
Limit Limondale 2 solar farm upper limit to 10 MW to manage post contingent voltage oscillation
N_LIMOSF21_CAP_23
18
Limit on a single plant
System Strength
MW conversion for Limondale Solar Farm 2 limit of 11.
N_LIMOSF2_FLT_15
2
Limit on a single plant
System Strength
Limit Limondale 2 solar farm upper limit to 15 MW to manage post contingent voltage oscillation
N_LIMOSF21_0INV
0
Equipment outage
Other
Limondale 2 Solar Farm inverter limit of zero. Constraint to violate if Limondale 2 Solar Farm inverter availability greater than zero. Swamp out otherwise. DS only
N_LIMOSF21_11_INV
0
Limit on a single plant
System Strength
Limondale 2 Solar Farm inverter limit of 11. Constraint to violate if Limondale 2 Solar Farm inverter availability greater than 11. Swamp out otherwise. DS only
LINE CPTS_RCTS_220, CB 2CAP_2B_66, LINE X9, BUS 7MN2, CB 1CAP_1B_66, CAP 2CAP_220
21 Sep 2026 06:00
21 Sep 2026 19:00
COMPLETE
HV equipt maintenance
10
RCTS
LINE CPTS_RCTS_220, CB 1CAP_1B_66, BUS 7MN2, CAP 2CAP_220, LINE X9, CB 2CAP_2B_66
22 Sep 2026 06:00
22 Sep 2026 19:00
COMPLETE
HV equipt maintenance
10
RCTS
LINE X9, CAP 2CAP_220, BUS 7MN2, LINE CPTS_RCTS_220
16 Oct 2026 05:00
16 Oct 2026 18:00
COMPLETE
HV equipt maintenance
8
BURONGA
LINE 6F
16 Oct 2026 05:00
16 Oct 2026 18:00
COMPLETE
HV equipt commissioning
8
RCTS
LINE CPTS_RCTS_220, BUS 7MN2, CAP 2CAP_220, LINE X9
15 Oct 2026 06:30
15 Oct 2026 19:30
COMPLETE
HV equipt maintenance
8
S_EAST, HYTS
LINE HYTS_SESS2_275
15 Oct 2026 07:00
15 Oct 2026 16:00
COMPLETE
HV equipt maintenance
7
KANGAROO, DAPTO
LINE 18
5 Sep 2026 08:00
6 Sep 2026 17:00
COMPLETE
HV equipt maintenance
4
SHTS, BETS
LINE BETS_SHTS_220
12 Oct 2026 11:00
23 Oct 2026 17:00
COMPLETE
HV equipt maintenance
2
–
N/A N/A
27 Oct 2026 06:00
29 Oct 2026 16:00
COMPLETE
HV equipt commissioning
0
WOTS, JINDERA
LINE N/A, LINE 060
28 Oct 2026 06:00
28 Oct 2026 17:00
COMPLETE
HV equipt maintenance
0
JINDERA, WOTS
LINE 060
28 Oct 2026 06:00
28 Oct 2026 17:00
COMPLETE
HV equipt maintenance
0
BURONGA
LINE 6F
28 Oct 2026 06:00
28 Oct 2026 17:00
COMPLETE
HV equipt commissioning
0
MULWALA
CB 7B1
28 Oct 2026 06:00
28 Oct 2026 17:00
COMPLETE
HV equipt maintenance
0
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.