Feeders between Yarranlea and Middle Ridge(733/1 and 734/1)

QLD · Thermal · Q>NIL_YLMR
Most frequent constraint: Out= Nil, avoid overload on 110kV feeders between Yarranlea and Middle Ridge(733/1 and 734/1), Feedback
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
72
% of period
3.3%
Network as built share
91%
Equipment outage share
0.0%
Single-plant limit share
8.7%
Units in constraints
2
MW in constraints
156
Curtailed while constrained
1.2 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
Q>NIL_YLMR65Network as builtThermalOut= Nil, avoid overload on 110kV feeders between Yarranlea and Middle Ridge(733/1 and 734/1), Feedback
Q_MARYRSF1_RB4Limit on a single plantDiscretionaryMaryrorough Run Back limit
Q_YARANSF1_RB4Limit on a single plantDiscretionaryYarrranlea Run Back limit
Q_YARANSF1_37MW_N-11Limit on a single plantUnit ZeroLimit Yarrenlea Solar Farm to 37 MW when feeder 733/1 or 733/3 or 734/1 or 734/3 (T10 Yarranlea to H14 Middle Ridge) trip, Swamp when the feeders are in service. DS formulation only

Units behind it

UnitFuelMWWeightDirection
Yarranlea Solar FarmSolar1211.00discharge
Maryrorough Solar FarmSolar341.00discharge

Associated outages

No associated outage overlapped this period.
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.