Most frequent constraint: Limit Haughton SF to 100% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
268
% of period
12%
Network as built share
0.0%
Equipment outage share
0.0%
Single-plant limit share
100%
Units in constraints
1
MW in constraints
133
Curtailed while constrained
3.4 GWh
Value of that curtailment
$0.1m
Network as built: the limit binds with every line and transformer in service. AEMO marks these “Out = Nil”.
Equipment outage: the limit applies only while a named line or transformer is out of service.
Limit on a single plant: AEMO caps one wind or solar farm. Most are system strength limits, which depend on how many coal, gas or hydro units and synchronous condensers are running nearby.
Constraint-hours by cause, per month
Network as builtEquipment outageLimit on a single plant
Constraints that bound in the period
Constraint
Hours
Cause
Limit type
AEMO description
Q_2+LCCP_HAUGHT11
265
Limit on a single plant
System Strength
Limit Haughton SF to 100% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_A39B_HAUGHT11
249
Limit on a single plant
System Strength
Limit Haughton SF to 100% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_2+RSVC_HAUGHT11
23
Limit on a single plant
System Strength
Limit Haughton SF to 100% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_2+3+VC_HAUGHT11
22
Limit on a single plant
System Strength
Limit Haughton SF to 100% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_STR_A19B_HASF
10
Limit on a single plant
System Strength
No limit to Haughton Solar Farm if Stan>=2+Cal>=1+Cal+Glad>=2+ (Stan+Cal+Glad) >=7, Kar>=2,NQLD>50&70(AVG,(Townsville GT>=1, if Kar,2) + Haughton syncon ON ,Zero otherwise.
Q_STR_NIL_HAUGHT11
2
Limit on a single plant
System Strength
Limit Haughton SF to 100%, 50%, 10% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton/Townsville/Clarke Creek Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_2+1_R4_HAUGHT11
2
Limit on a single plant
System Strength
Limit Haughton SF to100% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_A19A_HAUGHT11
0
Limit on a single plant
System Strength
Limit Haughton SF to 100%, 0% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
CB 5012, CB FDR_8552, LINE 275KV_855, CB CPLR_5052
14 Sep 2026 08:30
1 Oct 2026 18:00
COMPLETE
HV equipt commissioning
250
H13_ROSS
SVC 1_H13, CB SVC_5812, CB CPLR_5022
23 Sep 2026 13:32
24 Sep 2026 17:00
COMPLETE
HV equipt maintenance
21
H13_ROSS
SVC 1_H13, CB CPLR_5022, CB SVC_5812
23 Sep 2026 20:00
24 Sep 2026 12:00
COMPLETE
HV equipt maintenance
16
T34_MRNB, T110_PKD, H15_LILY
CB TFMR_4412, LINE 132KV_7382, TRANS X1, LINE 132KV_7124/1, LINE N/A, LINE 132KV_7114/1, LINE 7382
26 Sep 2026 07:30
26 Sep 2026 14:00
COMPLETE
HV equipt maintenance
6
T34_MRNB, T110_PKD, H15_LILY
CB TFMR_4422, TRANS X2, LINE 7382, LINE 132KV_7382, LINE 132KV_7114/1, LINE 132KV_7124/1, LINE N/A
24 Sep 2026 17:00
24 Sep 2026 23:59
COMPLETE
HV equipt maintenance
4
H13_ROSS
CB CPLR_5022, CB SVC_5812, SVC 1_H13
21 Sep 2026 19:42
22 Sep 2026 00:30
COMPLETE
HV equipt maintenance
2
Source: AEMO. Summary built 25 Nov 2026 02:26; data through 25 Nov 2026 01:25 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.