Most frequent constraint: Limit Aldoga SF to 100%, 80% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
315
% of period
15%
Network as built share
0.0%
Equipment outage share
0.0%
Single-plant limit share
100%
Units in constraints
1
MW in constraints
387
Curtailed while constrained
0.3 GWh
Value of that curtailment
$0.0m
Network as built: the limit binds with every line and transformer in service. AEMO marks these “Out = Nil”.
Equipment outage: the limit applies only while a named line or transformer is out of service.
Limit on a single plant: AEMO caps one wind or solar farm. Most are system strength limits, which depend on how many coal, gas or hydro units and synchronous condensers are running nearby.
Constraint-hours by cause, per month
Network as builtEquipment outageLimit on a single plant
Constraints that bound in the period
Constraint
Hours
Cause
Limit type
AEMO description
Q_A39B_ALDGASF1
153
Limit on a single plant
System Strength
Limit Aldoga SF to 100%, 80% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_2+LCCP_ALDGASF1
153
Limit on a single plant
System Strength
Limit Aldoga SF to 100% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_2+1_R3_ALDGASF1
80
Limit on a single plant
System Strength
Limit Aldoga SF to100% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_2+1_R4_ALDGASF1
60
Limit on a single plant
System Strength
Limit Aldoga SF to100% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_STR_ALDSF_ZERO
44
Limit on a single plant
System Strength
Limit Aldoga Solar farm to zero MW for system strength requirement
Q_2+RSVC_ALDGASF1
24
Limit on a single plant
System Strength
Limit Aldoga SF to 100% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_2+1_R2_ALDGASF1
19
Limit on a single plant
System Strength
Limit Aldoga SF to100% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
CB FDR_8632, CB FDR_8642, CB FDR_8612, LINE 275KV_8982, BUS 12, CB FDR_8622, CB FDR_88312, CB 5022
8 Oct 2026 09:00
8 Oct 2026 16:00
COMPLETE
HV equipt maintenance
1
H29_STAN
CB FDR_8642
8 Oct 2026 08:00
10 Oct 2026 16:30
COMPLETE
HV equipt maintenance
1
Source: AEMO. Summary built 25 Nov 2026 02:26; data through 25 Nov 2026 01:25 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.