Aldoga Solar Farm — system strength

QLD · System Strength · Q_A39B_ALDGASF1
Most frequent constraint: Limit Aldoga SF to 100%, 80% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
315
% of period
15%
Network as built share
0.0%
Equipment outage share
0.0%
Single-plant limit share
100%
Units in constraints
1
MW in constraints
387
Curtailed while constrained
0.3 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
Q_A39B_ALDGASF1153Limit on a single plantSystem StrengthLimit Aldoga SF to 100%, 80% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_2+LCCP_ALDGASF1153Limit on a single plantSystem StrengthLimit Aldoga SF to 100% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_2+1_R3_ALDGASF180Limit on a single plantSystem StrengthLimit Aldoga SF to100% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_2+1_R4_ALDGASF160Limit on a single plantSystem StrengthLimit Aldoga SF to100% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_STR_ALDSF_ZERO44Limit on a single plantSystem StrengthLimit Aldoga Solar farm to zero MW for system strength requirement
Q_2+RSVC_ALDGASF124Limit on a single plantSystem StrengthLimit Aldoga SF to 100% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_2+1_R2_ALDGASF119Limit on a single plantSystem StrengthLimit Aldoga SF to100% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
NC_Q_ALDGASF12Limit on a single plantNon-ConformanceNon Conformance Constraint for ALDOGA SOLAR FARM

Units behind it

UnitFuelMWWeightDirection
Aldoga Solar FarmSolar3871.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
275KV_8859, H58_LARCLINE 275KV_885921 Sep 2026 07:002 Oct 2026 17:00COMPLETEHV equipt maintenance153
H29_STAN, H24_CALVCB FDR_8552, CB 5012, CB CPLR_5052, LINE 275KV_85514 Sep 2026 08:301 Oct 2026 18:00COMPLETEHV equipt commissioning153
H11_NEBO, H20_BSNDCB CPLR_5042, LINE 275KV_8846, CB FDR_88462, CB CPLR_50627 Sep 2026 07:0013 Sep 2026 11:30COMPLETEHV equipt commissioning76
H13_ROSSCB CPLR_5022, CB SVC_5812, SVC 1_H1323 Sep 2026 13:3224 Sep 2026 17:00COMPLETEHV equipt maintenance21
H13_ROSSCB SVC_5812, CB CPLR_5022, SVC 1_H1323 Sep 2026 20:0024 Sep 2026 12:00COMPLETEHV equipt maintenance16
H35_STHM, H11_NEBOCB CPLR_5062, CB FDR_8222, LINE 275KV_82211 Sep 2026 07:0011 Sep 2026 17:00COMPLETEHV equipt maintenance10
H35_STHMSVC 1_H35, CB SVC_5812, CB CPLR_507211 Sep 2026 07:0011 Sep 2026 17:00COMPLETEHV equipt commissioning10
H11_NEBO, H20_BSNDCB CPLR_5042, LINE 275KV_8846, CB CPLR_5062, CB FDR_884629 Sep 2026 07:3013 Sep 2026 13:30COMPLETEHV equipt commissioning10
H35_STHM, H11_NEBOCB FDR_8222, CB CPLR_5062, LINE 275KV_82212 Sep 2026 07:0012 Sep 2026 17:00COMPLETEHV equipt maintenance9
H35_STHMSVC 1_H35, CB SVC_5812, CB CPLR_507212 Sep 2026 07:0012 Sep 2026 17:00COMPLETEHV equipt commissioning9
H20_BSNDCB FDR_8562, CB CPLR_5042, CB FDR_89342, BUS 1, CB FDR_8202, CB FDR_88312, CB FDR_892523 Oct 2026 09:306 Oct 2026 16:00COMPLETEHV equipt commissioning3
H13_ROSSCB SVC_5812, CB CPLR_5022, SVC 1_H1321 Sep 2026 19:4222 Sep 2026 00:30COMPLETEHV equipt maintenance2
H13_ROSSSVC 1_H1316 Sep 2026 18:0016 Sep 2026 19:30COMPLETEHV equipt maintenance1
H29_STANCB FDR_8632, CB FDR_8642, CB FDR_8612, LINE 275KV_8982, BUS 12, CB FDR_8622, CB FDR_88312, CB 50228 Oct 2026 09:008 Oct 2026 16:00COMPLETEHV equipt maintenance1
H29_STANCB FDR_86428 Oct 2026 08:0010 Oct 2026 16:30COMPLETEHV equipt maintenance1
Source: AEMO. Summary built 25 Nov 2026 02:26; data through 25 Nov 2026 01:25 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.