Mount Emerald — system strength

QLD · System Strength · Q_STR_A19B_MEWF
Most frequent constraint: Limit 80% to Mt Emerald Windfarm if Stan>=2+Cal>=1+Cal+Glad>=2+ (Stan+Cal+Glad) >=7, Kar>=2,NQLD>350&370(AVG),Ross_FN>150&170(AVG),(Townsville GT>=1if kar<2),40% If NQLD>50&70(AVG), Zero otherwise.
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
274
% of period
13%
Network as built share
0.0%
Equipment outage share
0.0%
Single-plant limit share
100%
Units in constraints
1
MW in constraints
181
Curtailed while constrained
14.8 GWh
Value of that curtailment
$1.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
Q_2+LCCP_MEWF180Limit on a single plantSystem StrengthLimit Mt Emerald WF to 100%, 80%, 25%, 15%, 1% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton/Townsville Syncon, NQLD demand, Ross+FNQ demand, NQLD WAMPAC; Zero if it does not meet the condition
Q_A39B_MEWF161Limit on a single plantSystem StrengthLimit Mt Emerald WF to 80%, 25%, 15%, 1% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton/Townsville Syncon, NQLD demand, Ross+FNQ demand, NQLD WAMPAC; Zero if it does not meet the condition
Q_2+1_R3_MEWF142Limit on a single plantSystem StrengthLimit Mt Emerald WF to100%,80%, 70%,25%,15%,1% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton/Townsville Syncon, NQLD demand, Ross+FNQ demand, NQLD WAMPAC; Zero if it does not meet the condition
Q_2+1_R4_MEWF134Limit on a single plantSystem StrengthLimit Mt Emerald WF to 100%,80%, 25%,15%,1% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton/Townsville Syncon, NQLD demand, Ross+FNQ demand, NQLD WAMPAC; Zero if it does not meet the condition
Q_2+BSNE_MEWF128Limit on a single plantSystem StrengthLimit Mt Emerald WF to 80%, 60%, 40%, 20% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton/Townsville Syncon, NQLD demand, Ross+FNQ demand, NQLD WAMPAC; Zero if it does not meet the condition
Q_2+3+VC_MEWF113Limit on a single plantSystem StrengthLimit Mt Emerald WF to 80%, 25%, 15%, 1% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton/Townsville Syncon, NQLD demand, Ross+FNQ demand, NQLD WAMPAC; Zero if it does not meet the condition
Q_2+1_R2_MEWF19Limit on a single plantSystem StrengthLimit Mt Emerald WF to100%,80%,25%,15% ,1% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton/Townsville Syncon, NQLD demand, Ross+FNQ demand, NQLD WAMPAC; Zero if it does not meet the condition
Q_A39_MEWF16Limit on a single plantSystem StrengthLimit Mt Emerald WF to 80%, 60%, 40%, 20% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton/Townsville Syncon, NQLD demand, Ross+FNQ demand, NQLD WAMPAC; Zero if it does not meet the condition
Q_2+RSVC_MEWF15Limit on a single plantSystem StrengthLimit Mt Emerald WF to 100%, 80%, 60%, 25%, 15%, 1% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton/Townsville Syncon, NQLD demand, Ross+FNQ demand, NQLD WAMPAC; Zero if it does not meet the condition
Q_STR_NIL_MEWF10Limit on a single plantSystem StrengthLimit Mt Emerald WF to 100%, 70%, 60% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton/Townsville/Clarke Creek Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_A19A_MEWF10Limit on a single plantSystem StrengthLimit Mt Emerald WF to 80%, 40%, 0% dependent on status of Stanwell, Callide B+C, Gladstone, Kareeya, Haughton Syncon, NQLD demand, Ross+FNQ demand; Zero if it does not meet the condition
Q_MEWF1_ZERO0Limit on a single plantUnit ZeroMt Emerald Wind Farm upper limit of 0 MW

Units behind it

UnitFuelMWWeightDirection
Mount EmeraldWind1811.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
275KV_8859, H58_LARCLINE 275KV_885921 Sep 2026 07:002 Oct 2026 17:00COMPLETEHV equipt maintenance80
H29_STAN, H24_CALVCB 5012, LINE 275KV_855, CB CPLR_5052, CB FDR_855214 Sep 2026 08:301 Oct 2026 18:00COMPLETEHV equipt commissioning80
H20_BSND, H11_NEBOLINE 275KV_8846, CB FDR_88462, CB CPLR_5062, CB CPLR_50427 Sep 2026 07:0013 Sep 2026 11:30COMPLETEHV equipt commissioning40
H20_BSND, H170_GLNCB CPLR_5042, LINE 275KV_8720, CB FDR_87192, CB FDR_8720213 Sep 2026 12:0020 Sep 2026 17:00COMPLETEHV equipt commissioning13
H170_GLN, H11_NEBOCB CPLR_5062, LINE 275KV_8846N, CB FDR_88462, CB CPLR_5022, CB FDR_87192, CB FDR_8720213 Sep 2026 12:0020 Sep 2026 17:00COMPLETEHV equipt commissioning13
H35_STHM, H11_NEBOCB FDR_8222, LINE 275KV_822, CB CPLR_506211 Sep 2026 07:0011 Sep 2026 17:00COMPLETEHV equipt maintenance6
H35_STHMCB SVC_5812, CB CPLR_5072, SVC 1_H3511 Sep 2026 07:0011 Sep 2026 17:00COMPLETEHV equipt commissioning6
H20_BSND, H11_NEBOCB CPLR_5062, CB FDR_88462, CB CPLR_5042, LINE 275KV_88469 Sep 2026 07:3013 Sep 2026 13:30COMPLETEHV equipt commissioning6
H13_ROSSCB CPLR_5022, CB SVC_5812, SVC 1_H1323 Sep 2026 13:3224 Sep 2026 17:00COMPLETEHV equipt maintenance5
H13_ROSSCB SVC_5812, CB CPLR_5022, SVC 1_H1323 Sep 2026 20:0024 Sep 2026 12:00COMPLETEHV equipt maintenance5
H35_STHM, H11_NEBOCB FDR_8222, CB CPLR_5062, LINE 275KV_82212 Sep 2026 07:0012 Sep 2026 17:00COMPLETEHV equipt maintenance3
H35_STHMCB CPLR_5072, SVC 1_H35, CB SVC_581212 Sep 2026 07:0012 Sep 2026 17:00COMPLETEHV equipt commissioning3
H20_BSNDCB FDR_88312, CB FDR_89252, CB FDR_8562, CB CPLR_5042, CB FDR_89342, BUS 1, CB FDR_82023 Oct 2026 09:306 Oct 2026 16:00COMPLETEHV equipt commissioning2
H13_ROSSCB CPLR_5022, CB SVC_5812, SVC 1_H1321 Sep 2026 19:4222 Sep 2026 00:30COMPLETEHV equipt maintenance0
H13_ROSSSVC 1_H1316 Sep 2026 18:0016 Sep 2026 19:30COMPLETEHV equipt maintenance0
Source: AEMO. Summary built 25 Nov 2026 02:26; data through 25 Nov 2026 01:25 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.