NEM Dashboard

ITK
Period

Templers to Dorrien

SA · Thermal · S>>NIL_TPWTX_TPDR
Most frequent constraint: Out= NIL, avoid O/L Templers to Dorrien 132kV line on trip of Templers West 132/275kV transformer, Feedback
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
13
% of period
0.6%
Network as built share
100%
Equipment outage share
0.0%
Single-plant limit share
0.0%
Units in constraints
1
MW in constraints
111
Curtailed while constrained
0.0 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
S>>NIL_TPWTX_TPDR13Network as builtThermalOut= NIL, avoid O/L Templers to Dorrien 132kV line on trip of Templers West 132/275kV transformer, Feedback

Units behind it

UnitFuelMWWeightDirection
Templers BESSBattery1111.00charge
Templers BESSBattery1111.00discharge
AngastonOther461.00charge

Associated outages

No associated outage overlapped this period.
Source: AEMO. Summary built 25 Nov 2026 02:56; data through 25 Nov 2026 01:55 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.