Most frequent constraint: Out= NIL, avoid O/L Tungkillo-Tailem Bend 275kV line 1 or 2 on trip of parallel Tungkillo-Tailem Bend 275 kV line 2 or 1, Feedback
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
5
% of period
0.3%
Network as built share
68%
Equipment outage share
32%
Single-plant limit share
0.0%
Units in constraints
0
MW in constraints
0
Curtailed while constrained
0.0 GWh
Value of that curtailment
$0.0m
Network as built: the limit binds with every line and transformer in service. AEMO marks these “Out = Nil”.
Equipment outage: the limit applies only while a named line or transformer is out of service.
Limit on a single plant: AEMO caps one wind or solar farm. Most are system strength limits, which depend on how many coal, gas or hydro units and synchronous condensers are running nearby.
Constraint-hours by cause, per month
Network as builtEquipment outageLimit on a single plant
Constraints that bound in the period
Constraint
Hours
Cause
Limit type
AEMO description
S>>NIL_TUTB_TUTB_1
4
Network as built
Thermal
Out= NIL, avoid O/L Tungkillo-Tailem Bend 275kV line 1 or 2 on trip of parallel Tungkillo-Tailem Bend 275 kV line 2 or 1, Feedback
CA_SYDS_59E0BEF5_1
2
Equipment outage
Thermal
Constraint Automation, O/L TUNTAB_1:LTB2:I:275@TUNKIL@SA for CTG LSIP on trip of TUNKIL - T_BEND #2 275KV LINE. Generated by STNET[BNECR3] Host NORREGEEMP8(EMPSYD)
Source: AEMO. Summary built 25 Nov 2026 02:56; data through 25 Nov 2026 01:55 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.