NEM Dashboard

ITK
Period

Redhill-Brinkworth T

SA · Thermal · S>NIL_BWMP_RHBR-T
Most frequent constraint: Out= Nil, avoid O/L Redhill-Brinkworth T 132kV line on trip of Blyth West-Munno Para 275kV line, Feedback
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
10
% of period
0.4%
Network as built share
100%
Equipment outage share
0.0%
Single-plant limit share
0.0%
Units in constraints
9
MW in constraints
956
Curtailed while constrained
0.1 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
S>NIL_BWMP_RHBR-T10Network as builtThermalOut= Nil, avoid O/L Redhill-Brinkworth T 132kV line on trip of Blyth West-Munno Para 275kV line, Feedback

Units behind it

UnitFuelMWWeightDirection
Blyth BESSBattery2000.29discharge
Bungama SolarBattery1500.29discharge
Snowtown S2 Wind FarmWind1440.29discharge
Waterloo Wind FarmWind1310.18charge
Snowtown S2 Wind FarmWind1260.29discharge
Snowtown Wind FarmWind990.70discharge
Wattle PointWind911.00discharge
Mintaro GTOCGT900.20charge
Mintaro GTOCGT900.17discharge
Clements Gap BESSBattery601.00discharge
Clements Gap Wind FarmWind571.00discharge
Dalrymple BESSBattery301.00discharge

Associated outages

No associated outage overlapped this period.
Source: AEMO. Summary built 25 Nov 2026 02:56; data through 25 Nov 2026 01:55 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.