Murraylink (SA side): Monash–North West Bend 132 kV

SA · Thermal · S>NIL_MHNW1_MHNW2
Most frequent constraint: Out= Nil, avoid O/L Monash-North West Bend #2 132kV on trip of Monash-North West Bend #1 132kV line, Feedback
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
372
% of period
17%
Network as built share
100%
Equipment outage share
0.0%
Single-plant limit share
0.0%
Units in constraints
0
MW in constraints
0
Curtailed while constrained
0.0 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
S>NIL_MHNW1_MHNW2372Network as builtThermalOut= Nil, avoid O/L Monash-North West Bend #2 132kV on trip of Monash-North West Bend #1 132kV line, Feedback

Units behind it

No units recorded for this area.

Associated outages

No associated outage overlapped this period.
Source: AEMO. Summary built 25 Nov 2026 02:26; data through 25 Nov 2026 01:25 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.