NEM Dashboard

ITK
Period

Snowtown WF

SA · Voltage Stability · S^SNWWF_60
Most frequent constraint: Out = Brinkworth-Redhill 132kV line (Redhill-Bungama section in service), Brinkworth-Redhill-Bungama line, Hummocks-Waterloo line or Bungama 275/132kV TX; limit Snowtown WF to 60MW to avoid voltage collapse on trip of Bungama TX or Hummocks-Waterloo line
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
11
% of period
0.5%
Network as built share
0.0%
Equipment outage share
100%
Single-plant limit share
0.0%
Units in constraints
1
MW in constraints
99
Curtailed while constrained
0.3 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
S^SNWWF_6011Equipment outageVoltage StabilityOut = Brinkworth-Redhill 132kV line (Redhill-Bungama section in service), Brinkworth-Redhill-Bungama line, Hummocks-Waterloo line or Bungama 275/132kV TX; limit Snowtown WF to 60MW to avoid voltage collapse on trip of Bungama TX or Hummocks-Waterloo line

Units behind it

UnitFuelMWWeightDirection
Snowtown Wind FarmWind991.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
HUMMOC, W_LOOCB CB6133, TRANS 1, TRANS T_1, CB CB6135, LINE HUMWAT_131 Aug 2026 08:001 Sep 2026 18:30COMPLETEHV equipt commissioning11
Source: AEMO. Summary built 25 Nov 2026 02:56; data through 25 Nov 2026 01:55 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.