Mount Beauty to Dederang (flow to North) for trip of the parallel
VIC · Thermal · V>>NIL_MBDD_MBDD
Most frequent constraint: Out = Nil, avoid O/L either Mount Beauty to Dederang 220 kV line (flow to North) for trip of the parallel line, feedback
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
4
% of period
0.2%
Network as built share
0.0%
Equipment outage share
100%
Single-plant limit share
0.0%
Units in constraints
36
MW in constraints
5,485
Curtailed while constrained
0.2 GWh
Value of that curtailment
$0.0m
Network as built: the limit binds with every line and transformer in service. AEMO marks these “Out = Nil”.
Equipment outage: the limit applies only while a named line or transformer is out of service.
Limit on a single plant: AEMO caps one wind or solar farm. Most are system strength limits, which depend on how many coal, gas or hydro units and synchronous condensers are running nearby.
Constraint-hours by cause, per month
Network as builtEquipment outageLimit on a single plant
Constraints that bound in the period
Constraint
Hours
Cause
Limit type
AEMO description
V>>DDSM_BEBA_DDSM
2
Equipment outage
Thermal
Out= Dederang to South Morang 330kV line, avoid O/L Bendigo to Ballarat 220kV line on trip of the remaining Dederang to South Morang 330kV line, Feedback
V>>DDTX3_DDT2_DD1_LH
1
Equipment outage
Thermal
Out= Dederang H3 txfmr, avoid O/L Dederang H2 220/330kV txfmr on trip of Dederang H1 220/330kV txfmr, Feedback
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.