Wemen transformer (Bannerton and Wemen solar farms)

VIC · Thermal · V>NIL_WETX_NIL
Most frequent constraint: Out = NIL, prevent pre-contingent overload of Wemen 220/66 kV txfmr, flow from 66 kV to 220 kV, feedback
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
303
% of period
14%
Network as built share
44%
Equipment outage share
0.0%
Single-plant limit share
56%
Units in constraints
2
MW in constraints
198
Curtailed while constrained
6.7 GWh
Value of that curtailment
$0.1m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
V>NIL_WETX_NIL153Network as builtThermalOut = NIL, prevent pre-contingent overload of Wemen 220/66 kV txfmr, flow from 66 kV to 220 kV, feedback
V_WEMENSF_FLT_45105Limit on a single plantSystem StrengthLimit Wemen Solar Farm upper limit to 45 MW to manage post contingent voltage oscillation
V_BANNERTSF_FLT_4585Limit on a single plantSystem StrengthLimit Bannerton Solar Farm upper limit to 45 MW to manage post contingent voltage oscillation
V_BANSF_BBD_S136Limit on a single plantDiscretionaryOut = Nil, Bannerton SF limitation segment 1 if Boundary Bend (BBD) loading is less than 5 MW, DS only. Swamp out if BBD loading is outside the range.
V_BANSF_BBD_S235Limit on a single plantDiscretionaryOut = Nil, Bannerton SF limitation segment 2 if Boundary Bend (BBD) loading is between 5 and 10 MW, DS only. Swamp out if BBD loading is outside the range.
V_BURC_WEMEN_SC_DYN5Limit on a single plantSystem StrengthOut = One Buronga to Red Cliffs (X1 or X9) 220kV line OR both Buronga syncon 4 & 5, Limit Wemen SF solar farm to 60 MW when Kiamal Syncon O/S. Swamp out if Kiamal Syncon is in service
V_BURC_BANN1_SC_DYN5Limit on a single plantSystem StrengthOut = One Buronga to Red Cliffs (X1 or X9) 220kV line OR both Buronga syncon 4 & 5, Limit Bannertonl solar farm to 60 MW when Kiamal Syncon O/S. Swamp out if Kiamal Syncon is in service
V_BANNERTSF_FLT_253Limit on a single plantSystem StrengthLimit Bannerton Solar Farm upper limit to 25 MW to manage post contingent voltage oscillation
V_WEMENSF_FLT_253Limit on a single plantSystem StrengthLimit Wemen Solar Farm upper limit to 25 MW to manage post contingent voltage oscillation
V_BANSF_BBD_S32Limit on a single plantDiscretionaryOut = Nil, Bannerton SF limitation segment 3 if Boundary Bend (BBD) loading is between 10 and 20 MW, DS only. Swamp out if BBD loading is outside the range.

Units behind it

UnitFuelMWWeightDirection
Bannerton Solar ParkSolar1001.00discharge
Wemen Solar FarmSolar981.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
TUMUT3, WAGGA330LINE 0515 Sep 2026 05:009 Sep 2026 18:00COMPLETEHV equipt commissioning40
BURONGA, BALRANLDLINE X5/3, LINE X311 Oct 2026 17:3015 Oct 2026 01:30COMPLETEHV equipt commissioning22
BURONGABUS B11 Oct 2026 17:3015 Oct 2026 01:30COMPLETEHV equipt commissioning22
BURONGALINE 6F11 Oct 2026 17:3015 Oct 2026 19:30COMPLETEHV equipt commissioning22
BURONGA, BALRANLDLINE X3, LINE X5/313 Sep 2026 05:0015 Sep 2026 19:00COMPLETEHV equipt commissioning16
KANGAROO, DAPTOLINE 185 Sep 2026 08:006 Sep 2026 17:00COMPLETEHV equipt maintenance14
RCTSLINE CPTS_RCTS_220, BUS 7MN2, CB 1CAP_1B_66, CB 2CAP_2B_66, LINE X9, CAP 2CAP_22022 Sep 2026 06:0022 Sep 2026 19:00COMPLETEHV equipt maintenance10
RCTSLINE CPTS_RCTS_220, LINE X9, CB 2CAP_2B_66, CAP 2CAP_220, BUS 7MN2, CB 1CAP_1B_6621 Sep 2026 06:0021 Sep 2026 19:00COMPLETEHV equipt maintenance9
S_EAST, HYTSLINE HYTS_SESS1_275, TRANS M1TR14 Oct 2026 07:0014 Oct 2026 16:00COMPLETEHV equipt maintenance9
RCTSLINE X9, CAP 2CAP_220, LINE CPTS_RCTS_220, BUS 7MN216 Oct 2026 05:0016 Oct 2026 18:00COMPLETEHV equipt maintenance8
BURONGALINE 6F16 Oct 2026 05:0016 Oct 2026 18:00COMPLETEHV equipt commissioning8
RCTSLINE CPTS_RCTS_220, BUS 7MN2, LINE X9, CAP 2CAP_22015 Oct 2026 06:3015 Oct 2026 19:30COMPLETEHV equipt maintenance8
S_EAST, HYTSLINE HYTS_SESS2_27515 Oct 2026 07:0015 Oct 2026 16:00COMPLETEHV equipt maintenance7
BURONGALINE X91 Sep 2026 07:001 Sep 2026 17:00COMPLETEHV equipt commissioning4
BURONGABUS B15 Sep 2026 13:0015 Sep 2026 19:00COMPLETEHV equipt commissioning4
BETS, SHTSLINE BETS_SHTS_22012 Oct 2026 11:0023 Oct 2026 17:00COMPLETEHV equipt maintenance3
RCTS, BURONGALINE 0X12 Sep 2026 07:002 Sep 2026 17:00COMPLETEHV equipt commissioning2
–N/A N/A27 Oct 2026 06:0029 Oct 2026 16:00COMPLETEHV equipt commissioning2
WOTS, JINDERALINE N/A, LINE 06028 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance2
JINDERA, WOTSLINE 06028 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance2
BURONGALINE 6F28 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt commissioning2
MULWALACB 7B128 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance2
BURONGABUS B13 Sep 2026 05:0013 Sep 2026 11:00COMPLETEHV equipt commissioning2
–N/A N/A15 Sep 2026 07:0015 Sep 2026 17:00MTLTPHV equipt commissioning0
BURONGASYNC SCON512 Sep 2026 16:0013 Sep 2026 17:00COMPLETEHV equipt commissioning0
Source: AEMO. Summary built 25 Nov 2026 02:26; data through 25 Nov 2026 01:25 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.