NSW · Voltage Stability · V^^N_CNCW_1
Most frequent constraint: Out = Canberra-Capital (6) or Kangaroo Valley to Capital (3W), avoid voltage collapse around Murray for loss of all APD potlines
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
171
% of period
7.9%
Network as built share
0.0%
Equipment outage share
100%
Single-plant limit share
0.0%
Units in constraints
1
MW in constraints
29
Curtailed while constrained
0.0 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
V^^N_CNCW_1171Equipment outageVoltage StabilityOut = Canberra-Capital (6) or Kangaroo Valley to Capital (3W), avoid voltage collapse around Murray for loss of all APD potlines

Units behind it

UnitFuelMWWeightDirection
Murray 1Water1,5500.09charge
Bogong / MackayWater3000.08charge
DartmouthWater1850.08charge
West KiewaWater680.08charge
GuthegaWater600.23charge
West KiewaWater340.08charge
Hume Dam NSWWater291.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
CAPITAL, CANBERRALINE 630 Sep 2026 07:0019 Oct 2026 16:00COMPLETEHV equipt maintenance102
CAPITAL, CANBERRALINE 628 Oct 2026 06:0016 Nov 2026 16:00COMPLETEHV equipt maintenance52
CAPITAL, CANBERRALINE 610 Sep 2026 07:0014 Sep 2026 17:00COMPLETEHV equipt maintenance9
CAPITAL, CANBERRALINE 62 Sep 2026 07:004 Sep 2026 17:00COMPLETEHV equipt maintenance8
CAPITAL, KANGAROOLINE 3W25 Aug 2026 07:3030 Aug 2026 18:00COMPLETEHV equipt commissioning2
SMTS, DDTSLINE DDTS_SMTS2_33030 Sep 2026 07:0030 Sep 2026 18:00COMPLETEHV equipt maintenance0
Source: AEMO. Summary built 25 Nov 2026 02:26; data through 25 Nov 2026 01:25 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.