| V^^V_NIL_KGTS | 105 | Network as built | Voltage Stability | Out= Nil, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line. Murraylink VFRB disabled. Swamp if Murraylink VFRB enabled. |
| V^^V_6CGH_KGTS | 98 | Equipment outage | Voltage Stability | Out= 6C, 6G, 6H 330kV lines, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line. Murraylink VFRB disabled. Swamp if Murraylink VFRB enabled |
| V^^V_MLNK_KGTS | 64 | Equipment outage | Voltage Stability | Out= Murraylink, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line |
| VS_HEY_600_TEST | 36 | Network as built | Other | Out = Nil, Vic to SA on Heywood limit of 600 MW, limit for testing of Heywood interconnection upgrade |
| I_6F_NS_150 | 28 | Limit on a single plant | Discretionary | Discretionary limit of 150 MW on Buronga to Bundey (6F) 330 kV Line (NSW to SA) |
| V^^V_BDBU_KGTS | 12 | Equipment outage | Voltage Stability | Out = Bundey to Buronga (6F) 330kV line, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line. Murraylink VFRB disabled. Swamp if Murraylink VFRB enabled. |
| V>>BDBU_ELML_BAML2 | 12 | Equipment outage | Thermal | Out = Bundey to Buronga (6F) 330kV line, avoid O/L Elaine to Moorabool 220kV line on trip of Ballarat to Moorabool No.2 220kV line, Feedback |
| V>>DDGN_GEDD_GNDD | 9 | Equipment outage | Thermal | Out = Glenrowan to Dederang No.1 or No.3 220kV line, avoid O/L Goorambat East to Dederang 220kV line on loss of remaining Glenrowan to Dederang 220kV line, feedback |
| V>>6CGH_ELML_BAML2 | 5 | Equipment outage | Thermal | Out= 6C, 6G, 6H 330kV lines, avoid O/L Elaine to Moorabool 220kV line on trip of Ballarat to Moorabool No.2 220kV line, Feedback |
| V>>NIL_WBBA_KGBE | 4 | Network as built | Thermal | Out= Nil, avoid O/L Waubra to Ballarat 220kV line on trip of Kerang to Bendigo 220kV line, Feedback |
| V_NWVIC_GEN_1100 | 4 | Limit on a single plant | Discretionary | 1100MW upper limit on IBR within North West Victoria (Bendigo-Ballarat-Red Cliffs 220kV area) |
| V>>X5_WBBA_KGBE | 3 | Equipment outage | Thermal | Out = Balranald to Darlington Pt (X5) 220kV line, avoid O/L Waubra to Ballarat 220kV line on trip of Kerang to Bendigo 220kV line, Feedback |
| V>>6CGH_WBBA_KGBE | 3 | Equipment outage | Thermal | Out= 6C, 6G, 6H 330kV lines, avoid O/L Waubra to Ballarat 220kV line on trip of Kerang to Bendigo 220kV line, Feedback |
| V_NWVIC_GEN_0600 | 2 | Limit on a single plant | Discretionary | 600MW upper limit on IBR within North West Victoria (Bendigo-Ballarat-Red Cliffs 220kV area) |
| V>>DDSM_MBEP_DDSM | 2 | Equipment outage | Thermal | Out= Dederang to South Morang 330 kV line, avoid O/L either Mount Beauty to Eildon 220 kV line on trip of remaining Dederang to South Morang 330 kV line, Feedback |
| V>>MLTG_ELML_BAML2 | 2 | Equipment outage | Thermal | Out= Moorabool to Terang 220kV line, avoid O/L Elaine to Moorabool 220kV line on trip of Ballarat to Moorabool No.2 220kV line, Feedback |
| V>>NIL_WBBA_RCWEKG | 2 | Network as built | Thermal | Out = Nil, avoid O/L Waubra to Ballarat 220kV line on trip of Red Cliffs to Wemen to Koorangie 220kV line (this trips off Bannerton and Wemen solar farms), Feedback |
| V>>6CGH_WBBA_RCWEKG | 2 | Equipment outage | Thermal | Out = 6C, 6G, 6H 330kV lines, avoid O/L Waubra to Ballarat 220kV line on trip of Red Cliffs to Wemen to Koorangie 220kV line (this trips off Bannerton and Wemen solar farms), Feedback |
| V^^V_NIL_KGTS_2 | 1 | Network as built | Voltage Stability | Out= Nil, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line. Murraylink VFRB enabled. Swamp if Murraylink VFRB disabled. |
| V>>X3_WBBA_KGBE | 0 | Equipment outage | Thermal | Out = Balranald to Buronga (X3) 220 kV line, avoid O/L Waubra to Ballarat 220kV line on trip of Kerang to Bendigo 220kV line, Feedback |
| V^^V_6CGH_KGTS_2 | 0 | Equipment outage | Voltage Stability | Out= 6C, 6G, 6H 330kV lines, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line. Murraylink VFRB enabled. Swamp if Murraylink VFRB disabled |
| V:S_BLKRG_570 | 0 | Equipment outage | Oscillatory Stability | Out = both or one Black Range series capacitors O/S, VIC to SA to on Heywood upper transfer limit of 570 MW based on oscillatory stability. |
| V>>6CGH_RCWE_HOMRKM | 0 | Equipment outage | Thermal | Out= 6C, 6G, 6H 330kV lines, avoid O/L Red Cliffs to Wemen 220kV line on trip of Horsham to Murra Warra to Kiamal 220kV line (this trips Murra Warra WF), Feedback |