NEM Dashboard

ITK
Period

Bulgana Green Power Hub — system strength

VIC · System Strength · V_BULGANAWF_FLT_0
Most frequent constraint: Limit Bulgana Wind Farm upper limit to 0 MW to manage system stability on the next contingency due to fault level issue
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
79
% of period
3.7%
Network as built share
0.0%
Equipment outage share
0.0%
Single-plant limit share
100%
Units in constraints
2
MW in constraints
224
Curtailed while constrained
2.2 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
V_BGWF_BESS_FLT_10072Limit on a single plantSystem StrengthLimit total output from Bulgana Wind Farm and Bulgana BESS to 100 MW to manage system stability on the next contingency due to fault level issue (voltage oscillation)
V_BULGANAWF_FLT_03Limit on a single plantSystem StrengthLimit Bulgana Wind Farm upper limit to 0 MW to manage system stability on the next contingency due to fault level issue
V_BULGANAWF_FLT_303Limit on a single plantSystem StrengthLimit Bulgana Wind Farm upper limit to 30 MW to manage post contingent voltage oscillation

Units behind it

UnitFuelMWWeightDirection
Bulgana Green Power Hub - Wind FarmWind2041.00discharge
Bulgana Green Power Hub - BESSBattery201.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
WAGGA330, TUMUT3LINE 0515 Sep 2026 05:009 Sep 2026 18:00COMPLETEHV equipt commissioning40
BURONGALINE 6F11 Oct 2026 17:3015 Oct 2026 19:30COMPLETEHV equipt commissioning19
BALRANLD, BURONGALINE X5/3, LINE X311 Oct 2026 17:3015 Oct 2026 01:30COMPLETEHV equipt commissioning19
BURONGABUS B11 Oct 2026 17:3015 Oct 2026 01:30COMPLETEHV equipt commissioning19
BALRANLD, BURONGALINE X3, LINE X5/313 Sep 2026 05:0015 Sep 2026 19:00COMPLETEHV equipt commissioning12
DAPTO, KANGAROOLINE 185 Sep 2026 08:006 Sep 2026 17:00COMPLETEHV equipt maintenance9
–N/A N/A11 Oct 2026 17:3011 Oct 2026 23:30COMPLETEHV equipt commissioning4
BURONGABUS B15 Sep 2026 13:0015 Sep 2026 19:00COMPLETEHV equipt commissioning4
–N/A N/A27 Oct 2026 06:0029 Oct 2026 16:00COMPLETEHV equipt commissioning3
JINDERA, WOTSLINE N/A, LINE 06028 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance3
SHTS, BETSLINE BETS_SHTS_22012 Oct 2026 11:0023 Oct 2026 17:00COMPLETEHV equipt maintenance3
JINDERA, WOTSLINE 06028 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance3
BURONGALINE 6F28 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt commissioning3
MULWALACB 7B128 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance3
–N/A N/A14 Oct 2026 21:0015 Oct 2026 01:30COMPLETEHV equipt commissioning3
BURONGABUS B13 Sep 2026 05:0013 Sep 2026 11:00COMPLETEHV equipt commissioning0
HYTS, S_EASTLINE HYTS_SESS1_275, TRANS M1TR14 Oct 2026 07:0014 Oct 2026 16:00SUBMITHV equipt maintenance0
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.