Most frequent constraint: Discretionary upper limit on Dundonnell WF (1 + 2 + 3) generation of 168 MW
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
191
% of period
8.8%
Network as built share
0.0%
Equipment outage share
1.4%
Single-plant limit share
99%
Units in constraints
5
MW in constraints
920
Curtailed while constrained
22.7 GWh
Value of that curtailment
$0.2m
Network as built: the limit binds with every line and transformer in service. AEMO marks these “Out = Nil”.
Equipment outage: the limit applies only while a named line or transformer is out of service.
Limit on a single plant: AEMO caps one wind or solar farm. Most are system strength limits, which depend on how many coal, gas or hydro units and synchronous condensers are running nearby.
Constraint-hours by cause, per month
Network as builtEquipment outageLimit on a single plant
Constraints that bound in the period
Constraint
Hours
Cause
Limit type
AEMO description
V_DUNDWF1_2_3_168
188
Limit on a single plant
Discretionary
Discretionary upper limit on Dundonnell WF (1 + 2 + 3) generation of 168 MW
V_V_HYAPD1_1
3
Equipment outage
Voltage Stability
Out = Heywood to Alcoa Portland 500kV No.1 line (HYTS-APD). Limit voltage unbalance at the APD 500 kV bus and Heywood 275 kV bus
V_DUNDWF_56WT
1
Limit on a single plant
System Strength
Dundonnell wind farm turbine limit of 56. Constraint to violate if Dundonnell Wind Farm number of turbine availability greater than 56. Swamp out otherwise. DS only
Source: AEMO. Summary built 25 Nov 2026 02:26; data through 25 Nov 2026 01:25 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.