Gannawarra Energy Storage System + Gannawarra Solar Farm — system strength
VIC · Islanding - Unit · V_GANWRSF_ISL_0
Most frequent constraint: Gannawarra Solar Farm upper limit of 0 MW to manage risk of islanding on the next contingency
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
113
% of period
5.2%
Network as built share
0.0%
Equipment outage share
0.1%
Single-plant limit share
100%
Units in constraints
2
MW in constraints
80
Curtailed while constrained
0.7 GWh
Value of that curtailment
$0.0m
Network as built: the limit binds with every line and transformer in service. AEMO marks these “Out = Nil”.
Equipment outage: the limit applies only while a named line or transformer is out of service.
Limit on a single plant: AEMO caps one wind or solar farm. Most are system strength limits, which depend on how many coal, gas or hydro units and synchronous condensers are running nearby.
Constraint-hours by cause, per month
Network as builtEquipment outageLimit on a single plant
Constraints that bound in the period
Constraint
Hours
Cause
Limit type
AEMO description
V_GANWRSF_FLT_30
62
Limit on a single plant
System Strength
Limit Gannawarra solar farm upper limit to 30 MW to manage post contingent voltage oscillation
V_GANWRSF_FLT_0
48
Limit on a single plant
System Strength
Limit Gannawarra solar farm upper limit to 0 MW to manage post contingent voltage oscillation
V_GANWRSF_FLT_15
3
Limit on a single plant
System Strength
Limit Gannawarra solar farm upper limit to 15 MW to manage post contingent voltage oscillation
V_GANWRSF_0INV
0
Equipment outage
Other
Gannawarra Solar Farm inverter limit of zero. Constraint to violate if Gannawarra Solar Farm inverter availability greater than zero. Swamp out otherwise. DS only
LINE CPTS_RCTS_220, CB 2CAP_2B_66, LINE X9, CAP 2CAP_220, CB 1CAP_1B_66, BUS 7MN2
21 Sep 2026 06:00
21 Sep 2026 19:00
COMPLETE
HV equipt maintenance
12
RCTS
LINE CPTS_RCTS_220, CB 1CAP_1B_66, BUS 7MN2, CB 2CAP_2B_66, LINE X9, CAP 2CAP_220
22 Sep 2026 06:00
22 Sep 2026 19:00
COMPLETE
HV equipt maintenance
12
RCTS
LINE CPTS_RCTS_220, BUS 7MN2, LINE X9, CAP 2CAP_220
15 Oct 2026 06:30
15 Oct 2026 19:30
COMPLETE
HV equipt maintenance
12
RCTS
CAP 2CAP_220, LINE X9, LINE CPTS_RCTS_220, BUS 7MN2
16 Oct 2026 05:00
16 Oct 2026 18:00
COMPLETE
HV equipt maintenance
12
BURONGA
LINE 6F
16 Oct 2026 05:00
16 Oct 2026 18:00
COMPLETE
HV equipt commissioning
12
S_EAST, HYTS
LINE HYTS_SESS2_275
15 Oct 2026 07:00
15 Oct 2026 16:00
COMPLETE
HV equipt maintenance
9
S_EAST, HYTS
LINE HYTS_SESS1_275, TRANS M1TR
14 Oct 2026 07:00
14 Oct 2026 16:00
COMPLETE
HV equipt maintenance
9
KANGAROO, DAPTO
LINE 18
5 Sep 2026 08:00
6 Sep 2026 17:00
COMPLETE
HV equipt maintenance
8
SHTS, BETS
LINE BETS_SHTS_220
12 Oct 2026 11:00
23 Oct 2026 17:00
COMPLETE
HV equipt maintenance
3
BURONGA
BUS B
15 Sep 2026 13:00
15 Sep 2026 19:00
COMPLETE
HV equipt commissioning
2
–
N/A N/A
27 Oct 2026 06:00
29 Oct 2026 16:00
COMPLETE
HV equipt commissioning
2
JINDERA, WOTS
LINE N/A, LINE 060
28 Oct 2026 06:00
28 Oct 2026 17:00
COMPLETE
HV equipt maintenance
2
JINDERA, WOTS
LINE 060
28 Oct 2026 06:00
28 Oct 2026 17:00
COMPLETE
HV equipt maintenance
2
BURONGA
LINE 6F
28 Oct 2026 06:00
28 Oct 2026 17:00
COMPLETE
HV equipt commissioning
2
MULWALA
CB 7B1
28 Oct 2026 06:00
28 Oct 2026 17:00
COMPLETE
HV equipt maintenance
2
BURONGA
BUS B
13 Sep 2026 05:00
13 Sep 2026 11:00
COMPLETE
HV equipt commissioning
2
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.