NEM Dashboard

ITK
Period

Karadoc Solar Farm — system strength

VIC · System Strength · V_KARADSF_FLT_25
Most frequent constraint: Limit Karadoc solar farm upper limit to 25 MW to manage post contingent voltage oscillation
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
134
% of period
6.2%
Network as built share
0.0%
Equipment outage share
0.0%
Single-plant limit share
100%
Units in constraints
1
MW in constraints
104
Curtailed while constrained
5.0 GWh
Value of that curtailment
$0.1m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
V_KARADSF_FLT_2596Limit on a single plantSystem StrengthLimit Karadoc solar farm upper limit to 25 MW to manage post contingent voltage oscillation
V_KARADSF_FLT_4530Limit on a single plantSystem StrengthLimit Karadoc solar Farm upper limit to 45 MW to manage post contingent voltage oscillation
V_BURC_KARSF1_SC_DYN8Limit on a single plantSystem StrengthOut = One Buronga to Red Cliffs (X1 or X9) 220kV line OR both Buronga syncon 4 & 5, Limit Karadoc solar farm to 60 MW when Kiamal Syncon O/S. Swamp out if Kiamal Syncon is in service

Units behind it

UnitFuelMWWeightDirection
Karadoc Solar FarmSolar1041.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
TUMUT3, WAGGA330LINE 0515 Sep 2026 05:009 Sep 2026 18:00COMPLETEHV equipt commissioning45
BURONGA, BALRANLDLINE X3, LINE X5/311 Oct 2026 17:3015 Oct 2026 01:30COMPLETEHV equipt commissioning28
BURONGABUS B11 Oct 2026 17:3015 Oct 2026 01:30COMPLETEHV equipt commissioning28
BURONGALINE 6F11 Oct 2026 17:3015 Oct 2026 19:30COMPLETEHV equipt commissioning28
BURONGA, BALRANLDLINE X5/3, LINE X313 Sep 2026 05:0015 Sep 2026 19:00COMPLETEHV equipt commissioning21
KANGAROO, DAPTOLINE 185 Sep 2026 08:006 Sep 2026 17:00COMPLETEHV equipt maintenance16
RCTSLINE X9, CB 2CAP_2B_66, CAP 2CAP_220, LINE CPTS_RCTS_220, CB 1CAP_1B_66, BUS 7MN222 Sep 2026 06:0022 Sep 2026 19:00COMPLETEHV equipt maintenance10
S_EAST, HYTSTRANS M1TR, LINE HYTS_SESS1_27514 Oct 2026 07:0014 Oct 2026 16:00SUBMITHV equipt maintenance9
RCTSBUS 7MN2, LINE X9, LINE CPTS_RCTS_220, CAP 2CAP_22016 Oct 2026 05:0016 Oct 2026 18:00COMPLETEHV equipt maintenance8
BURONGALINE 6F16 Oct 2026 05:0016 Oct 2026 18:00COMPLETEHV equipt commissioning8
RCTSCB 1CAP_1B_66, BUS 7MN2, CB 2CAP_2B_66, LINE X9, CAP 2CAP_220, LINE CPTS_RCTS_22021 Sep 2026 06:0021 Sep 2026 19:00COMPLETEHV equipt maintenance7
RCTSLINE X9, CAP 2CAP_220, LINE CPTS_RCTS_220, BUS 7MN215 Oct 2026 06:3015 Oct 2026 19:30COMPLETEHV equipt maintenance6
HYTS, S_EASTLINE HYTS_SESS2_27515 Oct 2026 07:0015 Oct 2026 16:00COMPLETEHV equipt maintenance5
BURONGALINE X91 Sep 2026 07:001 Sep 2026 17:00COMPLETEHV equipt commissioning5
BURONGABUS B15 Sep 2026 13:0015 Sep 2026 19:00COMPLETEHV equipt commissioning4
BURONGABUS B13 Sep 2026 05:0013 Sep 2026 11:00COMPLETEHV equipt commissioning3
BURONGA, RCTSLINE 0X12 Sep 2026 07:002 Sep 2026 17:00COMPLETEHV equipt commissioning2
–N/A N/A27 Oct 2026 06:0029 Oct 2026 16:00COMPLETEHV equipt commissioning2
JINDERA, WOTSLINE 060, LINE N/A28 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance2
WOTS, JINDERALINE 06028 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance2
BURONGALINE 6F28 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt commissioning2
MULWALACB 7B128 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance2
–N/A N/A15 Sep 2026 07:0015 Sep 2026 17:00MTLTPHV equipt commissioning0
BURONGASYNC SCON512 Sep 2026 16:0013 Sep 2026 17:00COMPLETEHV equipt commissioning0
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.