Kiamal Solar Farm — system strength

VIC · System Strength · V_KIAMSF_FLT_50
Most frequent constraint: Limit Kiamal solar farm upper limit to 50 MW to manage post contingent voltage oscillation
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
127
% of period
5.9%
Network as built share
0.0%
Equipment outage share
0.0%
Single-plant limit share
100%
Units in constraints
1
MW in constraints
200
Curtailed while constrained
5.0 GWh
Value of that curtailment
$0.1m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
V_KIAMSF_FLT_10074Limit on a single plantSystem StrengthLimit Kiamal Solar Farm upper limit to 100 MW to manage post contingent voltage oscillation
V_KIAMAL_ISL_048Limit on a single plantIslanding - UnitKiamal Solar Farm upper limit of 0 MW to manage risk of islanding on the next contingency
V_KIAMSF_FLT_603Limit on a single plantSystem StrengthLimit Kiamal solar farm upper limit to 60 MW to manage post contingent voltage oscillation
V_KIAMSF_FLT_501Limit on a single plantSystem StrengthLimit Kiamal solar farm upper limit to 50 MW to manage post contingent voltage oscillation
V_BURC_KIAMAL_SC_DYN0Limit on a single plantSystem StrengthOut = One Buronga to Red Cliffs (X1 or X9) 220kV line OR both Buronga syncon 4 & 5, Limit Kiamal solar farm to 180 MW when Kiamal Syncon O/S. Swamp out if Kiamal Syncon is in service

Units behind it

UnitFuelMWWeightDirection
Kiamal Solar Farm - Stage 1Solar2001.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
WAGGA330, TUMUT3LINE 0515 Sep 2026 05:009 Sep 2026 18:00COMPLETEHV equipt commissioning39
BALRANLD, BURONGALINE X5/3, LINE X311 Oct 2026 17:3015 Oct 2026 01:30COMPLETEHV equipt commissioning20
BURONGABUS B11 Oct 2026 17:3015 Oct 2026 01:30COMPLETEHV equipt commissioning20
BURONGALINE 6F11 Oct 2026 17:3015 Oct 2026 19:30COMPLETEHV equipt commissioning20
BURONGA, BALRANLDLINE X5/3, LINE X313 Sep 2026 05:0015 Sep 2026 19:00COMPLETEHV equipt commissioning16
KANGAROO, DAPTOLINE 185 Sep 2026 08:006 Sep 2026 17:00COMPLETEHV equipt maintenance14
RCTSCB 2CAP_2B_66, LINE X9, LINE CPTS_RCTS_220, CAP 2CAP_220, CB 1CAP_1B_66, BUS 7MN221 Sep 2026 06:0021 Sep 2026 19:00COMPLETEHV equipt maintenance12
RCTSLINE CPTS_RCTS_220, CB 1CAP_1B_66, BUS 7MN2, LINE X9, CB 2CAP_2B_66, CAP 2CAP_22022 Sep 2026 06:0022 Sep 2026 19:00COMPLETEHV equipt maintenance12
RCTSLINE CPTS_RCTS_220, BUS 7MN2, LINE X9, CAP 2CAP_22015 Oct 2026 06:3015 Oct 2026 19:30COMPLETEHV equipt maintenance12
RCTSLINE X9, CAP 2CAP_220, LINE CPTS_RCTS_220, BUS 7MN216 Oct 2026 05:0016 Oct 2026 18:00COMPLETEHV equipt maintenance12
BURONGALINE 6F16 Oct 2026 05:0016 Oct 2026 18:00COMPLETEHV equipt commissioning12
S_EAST, HYTSLINE HYTS_SESS1_275, TRANS M1TR14 Oct 2026 07:0014 Oct 2026 16:00COMPLETEHV equipt maintenance9
S_EAST, HYTSLINE HYTS_SESS2_27515 Oct 2026 07:0015 Oct 2026 16:00COMPLETEHV equipt maintenance9
BURONGABUS B15 Sep 2026 13:0015 Sep 2026 19:00COMPLETEHV equipt commissioning4
SHTS, BETSLINE BETS_SHTS_22012 Oct 2026 11:0023 Oct 2026 17:00COMPLETEHV equipt maintenance3
BURONGABUS B13 Sep 2026 05:0013 Sep 2026 11:00COMPLETEHV equipt commissioning1
–N/A N/A27 Oct 2026 06:0029 Oct 2026 16:00COMPLETEHV equipt commissioning1
WOTS, JINDERALINE N/A, LINE 06028 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance1
WOTS, JINDERALINE 06028 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance1
BURONGALINE 6F28 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt commissioning1
MULWALACB 7B128 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance1
BURONGALINE X91 Sep 2026 07:001 Sep 2026 17:00COMPLETEHV equipt commissioning0
BURONGA, RCTSLINE 0X12 Sep 2026 07:002 Sep 2026 17:00COMPLETEHV equipt commissioning0
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.