Most frequent constraint: Limit Kiata Wind Farm upper limit to 15 MW to manage system stability on the next contingency due to fault level issue
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
50
% of period
2.3%
Network as built share
0.0%
Equipment outage share
0.0%
Single-plant limit share
100%
Units in constraints
1
MW in constraints
31
Curtailed while constrained
0.3 GWh
Value of that curtailment
$0.0m
Network as built: the limit binds with every line and transformer in service. AEMO marks these “Out = Nil”.
Equipment outage: the limit applies only while a named line or transformer is out of service.
Limit on a single plant: AEMO caps one wind or solar farm. Most are system strength limits, which depend on how many coal, gas or hydro units and synchronous condensers are running nearby.
Constraint-hours by cause, per month
Network as builtEquipment outageLimit on a single plant
Constraints that bound in the period
Constraint
Hours
Cause
Limit type
AEMO description
V_KIATA_ISL_0
48
Limit on a single plant
Islanding - Unit
Kiata Wind Farm upper limit of 0 MW to manage risk of islanding on the next contingency
V_KIATAWF_FLT_10
2
Limit on a single plant
System Strength
Limit Kiata Wind Farm upper limit to 10 MW to manage post contingent voltage oscillation
LINE CPTS_RCTS_220, BUS 7MN2, CB 1CAP_1B_66, CB 2CAP_2B_66, LINE X9, CAP 2CAP_220
21 Sep 2026 06:00
21 Sep 2026 19:00
COMPLETE
HV equipt maintenance
12
RCTS
LINE CPTS_RCTS_220, CB 2CAP_2B_66, LINE X9, BUS 7MN2, CB 1CAP_1B_66, CAP 2CAP_220
22 Sep 2026 06:00
22 Sep 2026 19:00
COMPLETE
HV equipt maintenance
12
RCTS
LINE CPTS_RCTS_220, LINE X9, BUS 7MN2, CAP 2CAP_220
15 Oct 2026 06:30
15 Oct 2026 19:30
COMPLETE
HV equipt maintenance
12
RCTS
LINE X9, CAP 2CAP_220, LINE CPTS_RCTS_220, BUS 7MN2
16 Oct 2026 05:00
16 Oct 2026 18:00
COMPLETE
HV equipt maintenance
12
BURONGA
LINE 6F
16 Oct 2026 05:00
16 Oct 2026 18:00
COMPLETE
HV equipt commissioning
12
S_EAST, HYTS
LINE HYTS_SESS2_275
15 Oct 2026 07:00
15 Oct 2026 16:00
COMPLETE
HV equipt maintenance
9
SHTS, BETS
LINE BETS_SHTS_220
12 Oct 2026 11:00
23 Oct 2026 17:00
COMPLETE
HV equipt maintenance
2
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.