Mt Gellibrand Wind Farm — discretionary cap

VIC · Discretionary · V_MTGELIBRAND_66
Most frequent constraint: Mt Gelibrand wind farm upper limit of 66 MW
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
15
% of period
0.7%
Network as built share
0.0%
Equipment outage share
0.0%
Single-plant limit share
100%
Units in constraints
1
MW in constraints
139
Curtailed while constrained
0.4 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
V_MTGELIBRAND_6615Limit on a single plantDiscretionaryMt Gelibrand wind farm upper limit of 66 MW

Units behind it

UnitFuelMWWeightDirection
Mt Gellibrand Wind FarmWind1391.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
TGTSTRANS B26 Oct 2026 05:006 Oct 2026 17:30COMPLETEHV equipt maintenance11
MLTS, TGTSLINE MLTS_TGTS_2202 Oct 2026 06:302 Oct 2026 18:30COMPLETEHV equipt maintenance4
MLTS, TGTSLINE MLTS_TGTS_22014 Sep 2026 06:3014 Sep 2026 18:30COMPLETEHV equipt maintenance1
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.