Most frequent constraint: Limit Murra Warra Wind Farm 1+2 upper limit to 80 MW to manage system stability on the next contingency due to voltage oscillation
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
98
% of period
4.5%
Network as built share
0.0%
Equipment outage share
0.0%
Single-plant limit share
100%
Units in constraints
2
MW in constraints
435
Curtailed while constrained
10.2 GWh
Value of that curtailment
$0.4m
Network as built: the limit binds with every line and transformer in service. AEMO marks these “Out = Nil”.
Equipment outage: the limit applies only while a named line or transformer is out of service.
Limit on a single plant: AEMO caps one wind or solar farm. Most are system strength limits, which depend on how many coal, gas or hydro units and synchronous condensers are running nearby.
Constraint-hours by cause, per month
Network as builtEquipment outageLimit on a single plant
Constraints that bound in the period
Constraint
Hours
Cause
Limit type
AEMO description
V_MURRAWRWF_FLT_200
65
Limit on a single plant
System Strength
Limit Murra Warra Wind Farm 1+2 upper limit to 200 MW to manage system stability on the next contingency due to voltage oscillation
V_MURRAWRWF_FLT_15
32
Limit on a single plant
System Strength
Limit Murra Warra Wind Farm 1+2 upper limit to 15 MW to manage system stability on the next contingency due to voltage oscillation
V_MWWF2_SC_DYN
1
Limit on a single plant
Discretionary
Limit Murra Warra 2 WF to 100 MW when syncon at Murra Warra 2 WF O/S. DS only. Swamp out if Murra Warra 2 WF syncon in service
LINE CPTS_RCTS_220, BUS 7MN2, CB 1CAP_1B_66, CAP 2CAP_220, CB 2CAP_2B_66, LINE X9
21 Sep 2026 06:00
21 Sep 2026 19:00
COMPLETE
HV equipt maintenance
12
KANGAROO, DAPTO
LINE 18
5 Sep 2026 08:00
6 Sep 2026 17:00
COMPLETE
HV equipt maintenance
9
RCTS
CB 2CAP_2B_66, LINE X9, CAP 2CAP_220, LINE CPTS_RCTS_220, CB 1CAP_1B_66, BUS 7MN2
22 Sep 2026 06:00
22 Sep 2026 19:00
COMPLETE
HV equipt maintenance
9
BURONGA, BALRANLD
LINE X3, LINE X5/3
13 Sep 2026 05:00
15 Sep 2026 19:00
COMPLETE
HV equipt commissioning
7
RCTS
CAP 2CAP_220, BUS 7MN2, LINE CPTS_RCTS_220, LINE X9
16 Oct 2026 05:00
16 Oct 2026 18:00
COMPLETE
HV equipt maintenance
7
BURONGA
LINE 6F
16 Oct 2026 05:00
16 Oct 2026 18:00
COMPLETE
HV equipt commissioning
7
–
N/A N/A
14 Oct 2026 21:00
15 Oct 2026 01:30
COMPLETE
HV equipt commissioning
6
RCTS
LINE X9, CAP 2CAP_220, LINE CPTS_RCTS_220, BUS 7MN2
15 Oct 2026 06:30
15 Oct 2026 19:30
COMPLETE
HV equipt maintenance
5
HYTS, S_EAST
LINE HYTS_SESS2_275
15 Oct 2026 07:00
15 Oct 2026 16:00
COMPLETE
HV equipt maintenance
3
–
N/A N/A
11 Oct 2026 17:30
11 Oct 2026 23:30
COMPLETE
HV equipt commissioning
2
BURONGA
BUS B
15 Sep 2026 13:00
15 Sep 2026 19:00
COMPLETE
HV equipt commissioning
1
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.