NEM Dashboard

ITK
Period

North-west Victoria wind farms: combined output limit

VIC · Discretionary · V_NWVIC_GFT1_750
Most frequent constraint: Limit total output of Ararat, Crowlands, Bulgana (including BESS), Murra Warra 1 & 2 and Waubra wind farms to 750 MW
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
98
% of period
4.5%
Network as built share
0.0%
Equipment outage share
0.0%
Single-plant limit share
100%
Units in constraints
7
MW in constraints
1,010
Curtailed while constrained
8.0 GWh
Value of that curtailment
$0.3m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
V_NWVIC_GFT1_75098Limit on a single plantDiscretionaryLimit total output of Ararat, Crowlands, Bulgana (including BESS), Murra Warra 1 & 2 and Waubra wind farms to 750 MW

Units behind it

UnitFuelMWWeightDirection
Ararat Wind FarmWind2401.00discharge
Murra Warra Wind Farm - stage 1Wind2261.00discharge
Murra Warra Wind Farm - stage 2Wind2091.00discharge
Bulgana Green Power Hub - Wind FarmWind2041.00discharge
Crowlands Wind FarmWind801.00discharge
Kiata Wind FarmWind310.91discharge
Bulgana Green Power Hub - BESSBattery201.00discharge

Associated outages

No associated outage overlapped this period.
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.