Yatpool Solar Farm — system strength

VIC · System Strength · V_YATPSF_FLT_25
Most frequent constraint: Limit Yatpool solar farm upper limit to 25 MW to manage post contingent voltage oscillation
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Binding hours
81
% of period
3.7%
Network as built share
0.0%
Equipment outage share
0.0%
Single-plant limit share
100%
Units in constraints
1
MW in constraints
94
Curtailed while constrained
0.9 GWh
Value of that curtailment
$0.0m

Constraint-hours by cause, per month

Network as builtEquipment outageLimit on a single plant

Constraints that bound in the period

ConstraintHoursCauseLimit typeAEMO description
V_YATPSF_FLT_2576Limit on a single plantSystem StrengthLimit Yatpool solar farm upper limit to 25 MW to manage post contingent voltage oscillation
V_YATPSF_FLT_405Limit on a single plantSystem StrengthLimit Yatpool solar farm upper limit to 40 MW to manage post contingent voltage oscillation

Units behind it

UnitFuelMWWeightDirection
Yatpool Solar FarmSolar941.00discharge

Associated outages

SubstationEquipmentStartEndStatusReasonBinding hours (whole outage)
WAGGA330, TUMUT3LINE 0515 Sep 2026 05:009 Sep 2026 18:00COMPLETEHV equipt commissioning39
BALRANLD, BURONGALINE X3, LINE X5/311 Oct 2026 17:3015 Oct 2026 01:30COMPLETEHV equipt commissioning21
BURONGABUS B11 Oct 2026 17:3015 Oct 2026 01:30COMPLETEHV equipt commissioning21
BURONGALINE 6F11 Oct 2026 17:3015 Oct 2026 19:30COMPLETEHV equipt commissioning21
BETS, SHTSLINE BETS_SHTS_22012 Oct 2026 11:0023 Oct 2026 17:00COMPLETEHV equipt maintenance19
BALRANLD, BURONGALINE X3, LINE X5/313 Sep 2026 05:0015 Sep 2026 19:00COMPLETEHV equipt commissioning14
DAPTO, KANGAROOLINE 185 Sep 2026 08:006 Sep 2026 17:00COMPLETEHV equipt maintenance13
HYTS, S_EASTTRANS M1TR, LINE HYTS_SESS1_27514 Oct 2026 07:0014 Oct 2026 16:00COMPLETEHV equipt maintenance9
RCTSCAP 2CAP_220, BUS 7MN2, LINE X9, LINE CPTS_RCTS_22016 Oct 2026 05:0016 Oct 2026 18:00COMPLETEHV equipt maintenance4
BURONGALINE 6F16 Oct 2026 05:0016 Oct 2026 18:00COMPLETEHV equipt commissioning4
BURONGABUS B15 Sep 2026 13:0015 Sep 2026 19:00COMPLETEHV equipt commissioning3
BURONGABUS B13 Sep 2026 05:0013 Sep 2026 11:00COMPLETEHV equipt commissioning2
–N/A N/A27 Oct 2026 06:0029 Oct 2026 16:00COMPLETEHV equipt commissioning2
WOTS, JINDERALINE 060, LINE N/A28 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance2
WOTS, JINDERALINE 06028 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance2
BURONGALINE 6F28 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt commissioning2
MULWALACB 7B128 Oct 2026 06:0028 Oct 2026 17:00COMPLETEHV equipt maintenance2
S_EAST, HYTSLINE HYTS_SESS2_27515 Oct 2026 07:0015 Oct 2026 16:00COMPLETEHV equipt maintenance1
RCTSLINE X9, CAP 2CAP_220, LINE CPTS_RCTS_220, BUS 7MN215 Oct 2026 06:3015 Oct 2026 19:30COMPLETEHV equipt maintenance1
RCTSLINE CPTS_RCTS_220, BUS 7MN2, CB 1CAP_1B_66, CB 2CAP_2B_66, LINE X9, CAP 2CAP_22021 Sep 2026 06:0021 Sep 2026 19:00COMPLETEHV equipt maintenance0
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.