Bannerton Solar Park

Solar · VIC · BANN1
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Capacity
100 MW
Intervals limited
36%
Curtailed while constrained
10.7 GWh
Other curtailment
0.3 GWh
Value of constrained curtailment
$0.2m
Median local price adj.
−985 $/MWh

Share of intervals limited, by hour of day

Calendar months that overlap the period.

Share of intervals limited, by month

Constraints behind it

ConstraintAreaHoursDirectionAEMO description
N>>NIL_060_051Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV357dischargeOut= Nil, avoid O/L Jindera to Wodonga (60) 330kV line using 15 mins rating on trip of Wagga to Lower Tumut (051) 330kV line, Feedback
N>>6CGH_060_051Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV244dischargeOut= 6C, 6G, 6H 330kV lines, avoid O/L Jindera to Wodonga (60) 330kV line using 15 mins rating on trip of Wagga to Lower Tumut (051) 330kV line, Feedback
N^^N_6CGH_WGLTSouthern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV182dischargeOut=Nil, limit Wagga to Lower Tumut (51) 330kV line flow to avoid voltage collapse post contingency trip of line 51, Feedback
V>NIL_WETX_NILWemen transformer (Bannerton and Wemen solar farms)153dischargeOut = NIL, prevent pre-contingent overload of Wemen 220/66 kV txfmr, flow from 66 kV to 220 kV, feedback
V^^V_NIL_KGTSNorth-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV105dischargeOut= Nil, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line. Murraylink VFRB disabled. Swamp if Murraylink VFRB enabled.
V^^V_6CGH_KGTSNorth-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV98dischargeOut= 6C, 6G, 6H 330kV lines, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line. Murraylink VFRB disabled. Swamp if Murraylink VFRB enabled
V::N_NIL_V2Victoria: transient stability, Hazelwood–South Morang 500 kV95chargeOut = NIL, prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, VIC accelerates. Yallourn W G1 on 500kV.
V_BANNERTSF_FLT_45Wemen transformer (Bannerton and Wemen solar farms)85dischargeLimit Bannerton Solar Farm upper limit to 45 MW to manage post contingent voltage oscillation
N^^N_NIL_LTWGSouthern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV66chargeOut=Nil, limit Lower Tumut to Wagga 330kV line flow to avoid voltage collapse post contingency trip of line 51, Feedback
V^^V_MLNK_KGTSNorth-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV64dischargeOut= Murraylink, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line
N^^N_NIL_WGLTSouthern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV50dischargeOut=Nil, limit Wagga to Lower Tumut (051) 330kV line flow to avoid voltage collapse post contingency trip of line 51, Feedback
VS_HEY_600_TESTNorth-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV36chargeOut = Nil, Vic to SA on Heywood limit of 600 MW, limit for testing of Heywood interconnection upgrade
V_BANSF_BBD_S1Wemen transformer (Bannerton and Wemen solar farms)36dischargeOut = Nil, Bannerton SF limitation segment 1 if Boundary Bend (BBD) loading is less than 5 MW, DS only. Swamp out if BBD loading is outside the range.
V_BANSF_BBD_S2Wemen transformer (Bannerton and Wemen solar farms)35dischargeOut = Nil, Bannerton SF limitation segment 2 if Boundary Bend (BBD) loading is between 5 and 10 MW, DS only. Swamp out if BBD loading is outside the range.
V^^N_NIL_1Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV33chargeOut = Nil, avoid voltage collapse around Murray for loss of all APD potlines
Showing the 15 constraints with the most hours; 69 others also included this unit.
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.