NEM Dashboard

ITK
Period

Broken Hill

Battery · NSW · BHB1
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Capacity
50 MW
Intervals discharge-limited
43%
Intervals charge-limited
11%
Curtailed while constrained
0.0 GWh
Other curtailment
0.0 GWh
Value of constrained curtailment
$0.0m
Median local price adj.
−422 $/MWh

Share of intervals limited, by hour of day

Calendar months that overlap the period.

Share of intervals limited, by month

Constraints behind it

ConstraintAreaHoursDirectionAEMO description
N>>NIL_060_051Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV357dischargeOut= Nil, avoid O/L Jindera to Wodonga (60) 330kV line using 15 mins rating on trip of Wagga to Lower Tumut (051) 330kV line, Feedback
N>>6CGH_060_051Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV244dischargeOut= 6C, 6G, 6H 330kV lines, avoid O/L Jindera to Wodonga (60) 330kV line using 15 mins rating on trip of Wagga to Lower Tumut (051) 330kV line, Feedback
N^^N_6CGH_WGLTSouthern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV182dischargeOut=Nil, limit Wagga to Lower Tumut (51) 330kV line flow to avoid voltage collapse post contingency trip of line 51, Feedback
N^^N_NIL_WGLTSouthern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV178dischargeOut=Nil, limit Wagga to Lower Tumut (051) 330kV line flow to avoid voltage collapse post contingency trip of line 51, Feedback
N::N_CNCW_2Snowy to NSW: transient stability limits (Yass–Bannaby–Marulan)145dischargeOut = Canberra-Capital (6) line, stability limit (Snowy-NSW) for critical fault of one 330kV line between Yass and Bannaby/Marulan
N::N_SDUT_2Snowy to NSW: transient stability limits (Yass–Bannaby–Marulan)111dischargeOut = Upper Tumut-Stockdill (1) 330kV line, stability limit (Snowy-NSW) for fault of various location between Yass-South Morang area
V^^V_NIL_KGTSNorth-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV105dischargeOut= Nil, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line. Murraylink VFRB disabled. Swamp if Murraylink VFRB enabled.
V^^V_6CGH_KGTSNorth-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV98dischargeOut= 6C, 6G, 6H 330kV lines, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line. Murraylink VFRB disabled. Swamp if Murraylink VFRB enabled
N^^N_NIL_LTWGSouthern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV66chargeOut=Nil, limit Lower Tumut to Wagga 330kV line flow to avoid voltage collapse post contingency trip of line 51, Feedback
V^^V_MLNK_KGTSNorth-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV64dischargeOut= Murraylink, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line
N^^V_CNCW_1Southern NSW: voltage stability for loss of the largest Victorian unit or Basslink49chargeOut = Canberra-Capital (6) or Kangaroo Valley to Capital (3W) or Dapto-Kangaroo Valley (18), avoid voltage collapse at Darlington Point for loss of the largest Vic generating unit or Basslink
N^^V_NIL_1Southern NSW: voltage stability for loss of the largest Victorian unit or Basslink41chargeOut = Nil, avoid voltage collapse at Southern NSW for loss of the largest Vic generating unit or Basslink
VS_HEY_600_TESTNorth-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV36chargeOut = Nil, Vic to SA on Heywood limit of 600 MW, limit for testing of Heywood interconnection upgrade
V>>N_NIL_65_051Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV34dischargeOut = NIL, avoid O/L Murray to Upper Tumut (65) on trip of Wagga to Lower Tumut (051) line, Feedback
V^^N_NIL_1Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV33dischargeOut = Nil, avoid voltage collapse around Murray for loss of all APD potlines
Showing the 15 constraints with the most hours; 73 others also included this unit.
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.