| N>>NIL_060_051 | Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV | 151 | discharge | Out= Nil, avoid O/L Jindera to Wodonga (60) 330kV line using 15 mins rating on trip of Wagga to Lower Tumut (051) 330kV line, Feedback |
| V_NWVIC_GFT1_750 | North-west Victoria wind farms: combined output limit | 98 | discharge | Limit total output of Ararat, Crowlands, Bulgana (including BESS), Murra Warra 1 & 2 and Waubra wind farms to 750 MW |
| V^^V_6CGH_KGTS | North-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV | 98 | discharge | Out= 6C, 6G, 6H 330kV lines, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line. Murraylink VFRB disabled. Swamp if Murraylink VFRB enabled |
| V::N_NIL_V2 | Victoria: transient stability, Hazelwood–South Morang 500 kV | 95 | charge | Out = NIL, prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, VIC accelerates. Yallourn W G1 on 500kV. |
| V_BGWF_BESS_FLT_100 | Bulgana Green Power Hub — system strength | 72 | discharge | Limit total output from Bulgana Wind Farm and Bulgana BESS to 100 MW to manage system stability on the next contingency due to fault level issue (voltage oscillation) |
| V^^V_MLNK_KGTS | North-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV | 64 | discharge | Out= Murraylink, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line |
| I_6F_NS_150 | North-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV | 28 | discharge | Discretionary limit of 150 MW on Buronga to Bundey (6F) 330 kV Line (NSW to SA) |
| V::N_LTWG_S2 | Victoria: transient stability, Hazelwood–South Morang 500 kV | 21 | charge | Out = Lower Tumut to Wagga 330kV line, prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, SA accelerates, Yallourn W G1 on 500 kV. |
| V::N_SETB_V2 | Victoria: transient stability, Hazelwood–South Morang 500 kV | 17 | charge | Out = one South East - Tailembend 275kV line (Black Range series caps I/S), prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, VIC accelerates. Yallourn W G1 on 500kV. |
| V::N_NIL_V1 | Victoria: transient stability, Hazelwood–South Morang 500 kV | 15 | charge | Out = NIL, prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, VIC accelerates. Yallourn W G1 on 220kV. |
| V>>BELML_BAML1_BAML2 | Victoria: transient stability, Hazelwood–South Morang 500 kV | 14 | discharge | Out= Ballarat to Elaine to Moorabool 220kV line, avoid O/L Ballarat to Moorabool No.1 220kV line for trip of Ballarat to Moorabool No.2 220kV line, Feedback |
| V^^V_BDBU_KGTS | North-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV | 12 | discharge | Out = Bundey to Buronga (6F) 330kV line, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line. Murraylink VFRB disabled. Swamp if Murraylink VFRB enabled. |
| V>>BDBU_ELML_BAML2 | North-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV | 12 | discharge | Out = Bundey to Buronga (6F) 330kV line, avoid O/L Elaine to Moorabool 220kV line on trip of Ballarat to Moorabool No.2 220kV line, Feedback |
| V>>NIL_ELML_BAML2 | Victoria: transient stability, Hazelwood–South Morang 500 kV | 12 | discharge | Out= Nil, avoid O/L Elaine to Moorabool 220kV line on trip of Ballarat to Moorabool No.2 220kV line, Feedback |
| V::N_KGRC_V1 | Victoria: transient stability, Hazelwood–South Morang 500 kV | 11 | charge | Out = Kerang to Red Cliffs 220kV line (or any section in between), prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, VIC accelerates. Yallourn W G1 on 220kV. |