Bayswater

Coal · NSW · BW01
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Capacity
660 MW
Intervals limited
0.7%
Curtailed while constrained
0.0 GWh
Other curtailment
0.0 GWh
Value of constrained curtailment
$0.0m
Median local price adj.
−11 $/MWh

Share of intervals limited, by hour of day

Calendar months that overlap the period.

Share of intervals limited, by month

Constraints behind it

ConstraintAreaHoursDirectionAEMO description
N>>NIL_33_34Bayswater to Liddell (33 or 34) O/L on loss of other Bayswater to6dischargeOut= Nil, avoid Bayswater to Liddell (33 or 34) O/L on loss of other Bayswater to Liddell (34 or 33), Feedback
N>>33_34_QMAX_NBayswater to Liddell (33 or 34) O/L on loss of other Bayswater to3dischargeOut = Bayswater to Liddell(33 or 34), avoid O/L Bayswater to Liddell(33 or 34) on trip of QLD largest generation, Feedback
N>>81_964_82NSW mid-north coast: Port Macquarie–Herons Creek 132 kV3dischargeOut = Liddell to Newcastle (81) line, avoid O/L Port Macquarie to Herron Creek Tee (964/2) on trip of Liddell to Tomago (82) line, (Note: Swamps if 964 O/S)
N>>34+5A5_33_32Bayswater to Liddell (33 or 34) O/L on loss of other Bayswater to2dischargeOut= Mt. Piper-Wollar (5A5) and Bayswater to Liddell (33 or 34) line, avoid O/L Bayswater to Liddell (33 or 34) 330kV line on trip of Bayswater to Sydney West (32) 330kV line, Feedback
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.