NEM Dashboard

ITK
Period

Crowlands Wind Farm

Wind · VIC · CROWLWF1
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Capacity
80 MW
Intervals limited
16%
Curtailed while constrained
3.6 GWh
Other curtailment
7.9 GWh
Value of constrained curtailment
$0.0m
Median local price adj.
−191 $/MWh

Share of intervals limited, by hour of day

Calendar months that overlap the period.

Share of intervals limited, by month

Constraints behind it

ConstraintAreaHoursDirectionAEMO description
N>>NIL_060_051Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV151dischargeOut= Nil, avoid O/L Jindera to Wodonga (60) 330kV line using 15 mins rating on trip of Wagga to Lower Tumut (051) 330kV line, Feedback
V_NWVIC_GFT1_750North-west Victoria wind farms: combined output limit98dischargeLimit total output of Ararat, Crowlands, Bulgana (including BESS), Murra Warra 1 & 2 and Waubra wind farms to 750 MW
V::N_NIL_V2Victoria: transient stability, Hazelwood–South Morang 500 kV95chargeOut = NIL, prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, VIC accelerates. Yallourn W G1 on 500kV.
I_6F_NS_150North-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV28dischargeDiscretionary limit of 150 MW on Buronga to Bundey (6F) 330 kV Line (NSW to SA)
V::N_LTWG_S2Victoria: transient stability, Hazelwood–South Morang 500 kV21chargeOut = Lower Tumut to Wagga 330kV line, prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, SA accelerates, Yallourn W G1 on 500 kV.
NC_V_CROWLWF1Crowlands Wind Farm — system strength19dischargeNon Conformance Constraint for CROWLANDS WIND FARM
V::N_SETB_V2Victoria: transient stability, Hazelwood–South Morang 500 kV17chargeOut = one South East - Tailembend 275kV line (Black Range series caps I/S), prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, VIC accelerates. Yallourn W G1 on 500kV.
V::N_NIL_V1Victoria: transient stability, Hazelwood–South Morang 500 kV15chargeOut = NIL, prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, VIC accelerates. Yallourn W G1 on 220kV.
V>>BELML_BAML1_BAML2Victoria: transient stability, Hazelwood–South Morang 500 kV14dischargeOut= Ballarat to Elaine to Moorabool 220kV line, avoid O/L Ballarat to Moorabool No.1 220kV line for trip of Ballarat to Moorabool No.2 220kV line, Feedback
V>>BDBU_ELML_BAML2North-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV12dischargeOut = Bundey to Buronga (6F) 330kV line, avoid O/L Elaine to Moorabool 220kV line on trip of Ballarat to Moorabool No.2 220kV line, Feedback
V>>NIL_ELML_BAML2Victoria: transient stability, Hazelwood–South Morang 500 kV12dischargeOut= Nil, avoid O/L Elaine to Moorabool 220kV line on trip of Ballarat to Moorabool No.2 220kV line, Feedback
V::N_KGRC_V1Victoria: transient stability, Hazelwood–South Morang 500 kV11chargeOut = Kerang to Red Cliffs 220kV line (or any section in between), prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, VIC accelerates. Yallourn W G1 on 220kV.
V>>NIL_MLGT_MLGTVictoria: transient stability, Hazelwood–South Morang 500 kV8dischargeOut = NIL, avoid O/L Moorabool to Geelong #1 or #2 on trip of other Moorabool to Geelong line, Feedback
V::N_LTWG_V2Victoria: transient stability, Hazelwood–South Morang 500 kV7chargeOut = Lower Tumut to Wagga 330kV line, prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, VIC accelerates, Yallourn W G1 on 500 kV.
N^^V_MLNK_ARWBBASouthern NSW: voltage stability for loss of the largest Victorian unit or Basslink7dischargeOut = Murraylink, avoid voltage collapse in southern NSW for loss of Ballarat to Waubra to Ararat 220kV lines (this also trips Waubra, Ararat and Crowlands, Bulgana and Murra Warra WFs)
Showing the 15 constraints with the most hours; 39 others also included this unit.
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.