NEM Dashboard

ITK
Period

Eildon

Water · VIC · EILDON1
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Capacity
68 MW
Intervals limited
0.2%
Curtailed while constrained
0.0 GWh
Other curtailment
0.0 GWh
Value of constrained curtailment
$0.0m
Median local price adj.
−20 $/MWh

Share of intervals limited, by hour of day

Calendar months that overlap the period.

Share of intervals limited, by month

Constraints behind it

ConstraintAreaHoursDirectionAEMO description
V^^N_NIL_1Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV33chargeOut = Nil, avoid voltage collapse around Murray for loss of all APD potlines
V^^N_SDUT_1Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV11chargeOut = Stockdill to Upper Tumut (1) line, avoid voltage collapse around Murray for loss of all APD potlines
V^^N_BADP_1Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV10chargeOut = Balranald to Darlington Point (X5) 220kV line, avoid voltage collapse around Murray for loss of all APD potlines
V^^N_GRYS_1Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV7chargeOut = Gullen Range to Yass (3J), avoid voltage collapse around Murray for loss of all APD potlines
V^^N_BADP_DTKV_1Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV3chargeOut = Balranald to Darlington Point (X5) 220kV line and Dapto - Kangaroo Valley (18) 330kV line, avoid voltage collapse around Murray for loss of all APD potlines
V>>DDSM_BEBA_DDSMMount Beauty to Dederang (flow to North) for trip of the parallel2dischargeOut= Dederang to South Morang 330kV line, avoid O/L Bendigo to Ballarat 220kV line on trip of the remaining Dederang to South Morang 330kV line, Feedback
V>>DDSM_MBEP_DDSMNorth-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV2chargeOut= Dederang to South Morang 330 kV line, avoid O/L either Mount Beauty to Eildon 220 kV line on trip of remaining Dederang to South Morang 330 kV line, Feedback
V>>DDTX3_DDT2_DD1_LHMount Beauty to Dederang (flow to North) for trip of the parallel1dischargeOut= Dederang H3 txfmr, avoid O/L Dederang H2 220/330kV txfmr on trip of Dederang H1 220/330kV txfmr, Feedback
V^^N_DTMN_1Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV0chargeOut = Dapto to Marulan (8) 330kV Line, avoid voltage collapse around Murray for loss of all APD potlines
V>>SMF2_SMF1_NIL_R5The remaining South Morang 500/ F transformer0chargeOut = South Morang 500/330kV F2 transformer, avoid pre-contingent O/L of the remaining South Morang F1 500/330kV transformer, radial mode, YWPS unit 1 on 500kV, feedback
V^^N_DTSS_1Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV0chargeOut = Dapto-Sydney South(11), avoid voltage collapse around Murray for loss of all APD potlines
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.