Out = Balranald to Darlington Point (X5) 220kV line and Dapto - Kangaroo Valley (18) 330kV line, avoid voltage collapse around Murray for loss of all APD potlines
Out= Dederang to South Morang 330kV line, avoid O/L Bendigo to Ballarat 220kV line on trip of the remaining Dederang to South Morang 330kV line, Feedback
Out= Dederang to South Morang 330 kV line, avoid O/L either Mount Beauty to Eildon 220 kV line on trip of remaining Dederang to South Morang 330 kV line, Feedback
Out = South Morang 500/330kV F2 transformer, avoid pre-contingent O/L of the remaining South Morang F1 500/330kV transformer, radial mode, YWPS unit 1 on 500kV, feedback
Out = Dapto-Sydney South(11), avoid voltage collapse around Murray for loss of all APD potlines
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.