NEM Dashboard

ITK
Period

Golden Plains Wind Farm West

Wind · VIC · GPWFWST1
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Capacity
270 MW
Intervals limited
0.6%
Curtailed while constrained
0.8 GWh
Other curtailment
51.6 GWh
Value of constrained curtailment
$0.0m
Median local price adj.
−32 $/MWh

Share of intervals limited, by hour of day

Calendar months that overlap the period.

Share of intervals limited, by month

Constraints behind it

ConstraintAreaHoursDirectionAEMO description
V>>NIL_MLGT_MLGTVictoria: transient stability, Hazelwood–South Morang 500 kV8dischargeOut = NIL, avoid O/L Moorabool to Geelong #1 or #2 on trip of other Moorabool to Geelong line, Feedback
NC_V_GPWFWST1Commissioning / hold point constraint for Golden Plains Wind Farm West2dischargeNon Conformance Constraint for GPWF WEST 1
V>>6CGH_MLGT_MLGTVictoria: transient stability, Hazelwood–South Morang 500 kV1dischargeOut = NIL, avoid O/L Moorabool to Geelong #1 or #2 on trip of other Moorabool to Geelong line, Feedback
V_GPWFWST1_FLT_0Commissioning / hold point constraint for Golden Plains Wind Farm West1dischargeLimit Golden Plains wind farm Stage 2 Central Collector Group upper limit to 0MW for system strength requirement
V_GPWFWST1_0WTCommissioning / hold point constraint for Golden Plains Wind Farm West1dischargeGolden Plains wind farm Stage 2 Central Collector Group turbine availability limit of 0. Constraint to violate if Golden Plains wind farm Stage 2 Central Collector Group turbine availability greater than 0. Swamp out otherwise. DS only
V_GPWFWST1_ZEROCommissioning / hold point constraint for Golden Plains Wind Farm West1dischargeGolden Plains wind farm Stage 2 Central Collector Group upper limit of 0 MW
V>>SMF2_SMF1_NIL_R5The remaining South Morang 500/ F transformer0dischargeOut = South Morang 500/330kV F2 transformer, avoid pre-contingent O/L of the remaining South Morang F1 500/330kV transformer, radial mode, YWPS unit 1 on 500kV, feedback
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.