Kerang Solar Plant

Solar · VIC · KERNGSP1
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Capacity
30 MW
Intervals limited
13%
Curtailed while constrained
2.5 GWh
Other curtailment
7.1 GWh
Value of constrained curtailment
$0.0m
Median local price adj.
−301 $/MWh

Share of intervals limited, by hour of day

Calendar months that overlap the period.

Share of intervals limited, by month

Constraints behind it

ConstraintAreaHoursDirectionAEMO description
N>>NIL_060_051Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV151dischargeOut= Nil, avoid O/L Jindera to Wodonga (60) 330kV line using 15 mins rating on trip of Wagga to Lower Tumut (051) 330kV line, Feedback
V^^V_NIL_KGTSNorth-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV105chargeOut= Nil, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line. Murraylink VFRB disabled. Swamp if Murraylink VFRB enabled.
V^^V_6CGH_KGTSNorth-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV98chargeOut= 6C, 6G, 6H 330kV lines, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line. Murraylink VFRB disabled. Swamp if Murraylink VFRB enabled
V::N_NIL_V2Victoria: transient stability, Hazelwood–South Morang 500 kV95chargeOut = NIL, prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, VIC accelerates. Yallourn W G1 on 500kV.
N^^N_NIL_LTWGSouthern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV66chargeOut=Nil, limit Lower Tumut to Wagga 330kV line flow to avoid voltage collapse post contingency trip of line 51, Feedback
V^^V_MLNK_KGTSNorth-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV64chargeOut= Murraylink, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line
N^^N_NIL_WGLTSouthern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV50dischargeOut=Nil, limit Wagga to Lower Tumut (051) 330kV line flow to avoid voltage collapse post contingency trip of line 51, Feedback
VS_HEY_600_TESTNorth-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV36chargeOut = Nil, Vic to SA on Heywood limit of 600 MW, limit for testing of Heywood interconnection upgrade
V^^N_NIL_1Southern NSW: Jindera–Wodonga and Wagga–Lower Tumut 330 kV33chargeOut = Nil, avoid voltage collapse around Murray for loss of all APD potlines
I_6F_NS_150North-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV28dischargeDiscretionary limit of 150 MW on Buronga to Bundey (6F) 330 kV Line (NSW to SA)
V::N_LTWG_S2Victoria: transient stability, Hazelwood–South Morang 500 kV21chargeOut = Lower Tumut to Wagga 330kV line, prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, SA accelerates, Yallourn W G1 on 500 kV.
V::N_SETB_V2Victoria: transient stability, Hazelwood–South Morang 500 kV17chargeOut = one South East - Tailembend 275kV line (Black Range series caps I/S), prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, VIC accelerates. Yallourn W G1 on 500kV.
V::N_NIL_V1Victoria: transient stability, Hazelwood–South Morang 500 kV15chargeOut = NIL, prevent transient instability for fault and trip of a HWTS-SMTS 500 kV line, VIC accelerates. Yallourn W G1 on 220kV.
V>>BELML_BAML1_BAML2Victoria: transient stability, Hazelwood–South Morang 500 kV14dischargeOut= Ballarat to Elaine to Moorabool 220kV line, avoid O/L Ballarat to Moorabool No.1 220kV line for trip of Ballarat to Moorabool No.2 220kV line, Feedback
V^^V_BDBU_KGTSNorth-west Victoria: voltage stability, Horsham–Murra Warra–Kiamal 220 kV12chargeOut = Bundey to Buronga (6F) 330kV line, avoid voltage collapse for loss of Horsham - Murra Warra - Kiamal 220kV line. Murraylink VFRB disabled. Swamp if Murraylink VFRB enabled.
Showing the 15 constraints with the most hours; 58 others also included this unit.
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.