Moree Solar Farm

Solar · NSW · MOREESF1
Period, last 90 days (27 Aug 2026 to 24 Nov 2026, 2,160 hours).
Capacity
56 MW
Intervals limited
26%
Curtailed while constrained
1.5 GWh
Other curtailment
0.0 GWh
Value of constrained curtailment
$0.1m
Median local price adj.
−330 $/MWh

Share of intervals limited, by hour of day

Calendar months that overlap the period.

Share of intervals limited, by month

Constraints behind it

ConstraintAreaHoursDirectionAEMO description
N>NIL_969North-west NSW: Gunnedah–Tamworth 132 kV412dischargeOut= Nil, avoid O/L Gunnedah to Tamworth (969) on trip of Nil, Feedback. Metering is used as specified in OM520 [Note: swamped with 96M or 9UJ or 9UH or 9U3/2 is O/S]
N>>NIL_964_84_SNSW mid-north coast: Port Macquarie–Herons Creek 132 kV259dischargeOut= NIL, avoid O/L Port Macquarie to Herons Creek Tee (964/2) on trip of Tamworth to Liddell (84) line, Feedback
N>NIL_MORTX_LVNorth-west NSW: Gunnedah–Tamworth 132 kV161dischargeNIL, avoid O/L Moree (1 or 2) 66/132kV TX on trip of Moree (2 or 1) 66/132kV TX, Feedback
N>>NIL_85_86_SNSW mid-north coast: Port Macquarie–Herons Creek 132 kV60dischargeOut= NIL, avoid O/L Uralla to Tamworth (85) on trip of Armidale to Tamworth (86) line, Feedback
N>>NIL_86_85_SNSW mid-north coast: Port Macquarie–Herons Creek 132 kV15dischargeOut= NIL, avoid O/L Armidale to Tamworth (86) on trip of Uralla to Tamworth (85) line, Feedback
N>>NIL_33_34Bayswater to Liddell (33 or 34) O/L on loss of other Bayswater to6chargeOut= Nil, avoid Bayswater to Liddell (33 or 34) O/L on loss of other Bayswater to Liddell (34 or 33), Feedback
N>>965_9W2_9W8NSW mid-north coast: Port Macquarie–Herons Creek 132 kV6dischargeOut= Armidale to Kempsey (965), avoid O/L Raliegh to Kempsey 132kV line on trip of Coffs Harbour to Boambee (9W8) 132kV line, Feedback
N>>9W7_9W2_965NSW mid-north coast: Port Macquarie–Herons Creek 132 kV5dischargeOut= One of Coffs Harbour to Kempsey (9W5 or 9W6 or 9W7 or 9W8), avoid O/L Raliegh to Kempsey (9W2) 132kV line on trip of Armidale to Kempsey (965) 132kV line, Feedback
N>9U2_969_NILNorth-west NSW: Gunnedah–Tamworth 132 kV4dischargeOut= 9U2 (Moree to Inverell ) 132kV line, avoid O/L on 969 (Gunnedah to Tamworth) 132 kV on Nil trip, Feedback
N>>33_34_QMAX_NBayswater to Liddell (33 or 34) O/L on loss of other Bayswater to3chargeOut = Bayswater to Liddell(33 or 34), avoid O/L Bayswater to Liddell(33 or 34) on trip of QLD largest generation, Feedback
N>>86_85_NIL_SNSW mid-north coast: Port Macquarie–Herons Creek 132 kV3dischargeOut= Tamworth-Armidale(86), avoid O/L Uralla to Tamworth (85) 330kV line on trip of Nil, Feedback [Note: Assumed Armidale-Moree-Tamworth parrellel open (96M OPEN),Armidale-Kempsey-Newcastle 132kV parrallel open (964 OPEN)]
N>>81_964_82NSW mid-north coast: Port Macquarie–Herons Creek 132 kV3dischargeOut = Liddell to Newcastle (81) line, avoid O/L Port Macquarie to Herron Creek Tee (964/2) on trip of Liddell to Tomago (82) line, (Note: Swamps if 964 O/S)
N>>NIL_8U_86_SNSW mid-north coast: Port Macquarie–Herons Creek 132 kV2dischargeOut= NIL, avoid O/L Armidale to Uralla (8U) on trip of Armidale to Tamworth (86) line, Feedback
N>>34+5A5_33_32Bayswater to Liddell (33 or 34) O/L on loss of other Bayswater to2chargeOut= Mt. Piper-Wollar (5A5) and Bayswater to Liddell (33 or 34) line, avoid O/L Bayswater to Liddell (33 or 34) 330kV line on trip of Bayswater to Sydney West (32) 330kV line, Feedback
N>>964_85_86_SNSW mid-north coast: Port Macquarie–Herons Creek 132 kV0dischargeOut= Taree to Port Macquarie (964) 132kV line, avoid O/L Uralla to Tamworth (85) on trip of Armidale to Tamworth (86) line, Feedback
Showing the 15 constraints with the most hours; 7 others also included this unit.
Source: AEMO. Summary built 25 Nov 2026 02:41; data through 25 Nov 2026 01:40 NEM time. “Intervals limited” measures exposure (a binding constraint that includes the unit), not lost output. “Curtailed while constrained” is the unit’s curtailment in intervals when such a constraint was binding, valued at the regional price with negative prices counted as zero. Constraint definitions arrive from AEMO about a month after the event, so recent constraints show “description pending”.